Uranium term prices are at record highs, but third-quarter 2026 results show two very different stages of Canada's uranium sector. Cameco Corp. (TSX:CCO) is an established producer. It earned more on a reported basis than a year earlier, but its adjusted results weakened because of lower Westinghouse earnings, lower sales volumes and higher unit costs. Denison Mines Corp. (TSX:DML) is building its Phoenix in-situ recovery (ISR) mine. Its quarter was about construction progress, spending and contracting, not revenue. For both companies, the price backdrop is supportive. The long-term uranium price indicator reached US$99 per pound at the end of October.
The uranium price backdrop
According to Cameco's (TSX:CCO) third-quarter management's discussion and analysis (MD&A), the uranium Spot Price was US$89.63 per pound on 30 September 2026. The long-term price was US$96.50, up US$13.50 from a year earlier. The long-term price indicator rose to US$99.00 at the end of October, the highest level since the series began in 1996. On 10 November, uranium futures were above US$91 per pound, their highest level since February, supported by a stronger nuclear outlook, a higher International Atomic Energy Agency capacity forecast and power deals for AI data centres.
Term prices matter more than spot prices for these companies, because utilities buy most of their uranium under multi-year contracts. Producers with uncommitted pounds to sell, and developers that are signing their first sales agreements, can benefit most from a rising term market.
Cameco's quarter: higher reported profit, softer adjusted results
Cameco (TSX:CCO) reported net Earnings attributable to shareholders of $43 million, or $0.10 per share, for the quarter ended 30 September. That compared with roughly break-even a year earlier. Revenue edged up to $619 million from $615 million. On an adjusted basis, Cameco (TSX:CCO) posted a $2 million loss, compared with adjusted earnings of $32 million in the third quarter of 2025. Adjusted EBITDA fell to $267 million from $310 million. Nine-month adjusted net earnings were $279 million, down from $410 million.
Cameco (TSX:CCO) said the main reasons were lower Equity earnings from Westinghouse, lower sales volumes and a higher average unit cost of sales, partly offset by higher realized prices. The annual maintenance shutdown at the Key Lake mill ran longer than usual because of major projects to support long-term operations. Cameco (TSX:CCO) narrowed its 2026 production guidance to 19.5–20.5 million pounds, from 19.5–21.5 million pounds. It narrowed sales guidance to 29.5–30.5 million pounds. The board declared an annual Dividend of $0.24 per share, payable on 15 December 2026. Cameco's (TSX:CCO) shares closed at $116.63 on the Toronto Stock Exchange on 30 October.
Westinghouse: weaker earnings, bigger pipeline
Cameco (TSX:CCO) owns 49 per cent of Westinghouse. Its share of Westinghouse's third-quarter net loss was $24 million, compared with a $32 million loss a year earlier. Its share of adjusted EBITDA rose to $143 million from $124 million. For the nine months, however, the comparison was much weaker. Cameco (TSX:CCO) noted that 2025 had been boosted by about US$170 million of Westinghouse revenue tied to the Dukovany project in the Czech Republic.
The longer-term story has moved forward. Cameco's (TSX:CCO) MD&A says a non-binding framework with the Republic of Korea in September 2026 anticipates up to US$120 billion of Investment to help fund up to eight large US reactors, including six AP1000 units. The framework builds on the 2025 Partnership between Cameco (TSX:CCO), Brookfield and the US government. It still depends on definitive agreements. In October, the US Nuclear Regulatory Commission renewed the AP1000 design certification through 2066.
Denison: Phoenix construction at 24 per cent
Denison (TSX:DML) reported its third-quarter results on 4 November. Phoenix, at the company's Wheeler River project in northern Saskatchewan, was about 24 per cent complete at 30 September, after the first quarter of full-scale construction that started in July. Denison (TSX:DML) still targets completion of construction and first production in the second half of 2028. Year-to-date Phoenix spending was $161.1 million, and 2026 spending is forecast at $278.6 million. The MD&A estimates that unusual weather and flooding events added about $20 million to construction and engineering costs. It says the schedule and cost to completion are expected to be finalized in early 2027. Post-final-investment-decision initial Capital is currently estimated at $600 million, in 2026 dollars.
Denison (TSX:DML) held about $362.7 million in cash and cash equivalents at the end of the quarter, down from $465.9 million at the end of 2025. It also held 950,000 pounds of physical uranium, valued at about $121 million. Its convertible notes due 2031 have a Face Value of US$345 million. Mainly because of non-cash Fair Value changes on those notes, Denison (TSX:DML) reported third-quarter net earnings of $81.8 million and an adjusted net loss of $28.7 million. Its firm sales commitments total more than eight million pounds, with negotiations under way for more than five million more. That includes 350,000 pounds fixed at an average of about US$95 per pound.
Key risks for Canadian uranium stocks
Each company has its own risks. For Cameco (TSX:CCO), these include operating disruptions at its Saskatchewan mills and mines and volatile Westinghouse earnings. The large US reactor frameworks may also never become binding contracts. For Denison (TSX:DML), the risks include cost overruns, construction delays, northern weather and funding needs before Phoenix produces any revenue. Both companies are exposed to uranium price volatility, policy shifts and changes in investor sentiment toward nuclear and AI-related energy stocks.
Conclusion
Cameco (TSX:CCO) and Denison (TSX:DML) both reflect strong uranium term pricing, but at different stages. Cameco's (TSX:CCO) third quarter showed how Westinghouse and Key Lake timing can affect a producer's results even when prices are high. Denison's (TSX:DML) report showed that Phoenix construction is progressing, while costs need watching. Upcoming items to monitor include Cameco's (TSX:CCO) 2027 outlook, any definitive US reactor agreements involving Westinghouse, and Denison's (TSX:DML) updated Phoenix cost and schedule estimate in early 2027.