Pulsar Helium Inc. (TSXV:PLSR) plans to move its Topaz project in northeastern Minnesota from appraisal to commercial helium production. Its plan has three parts. First, it would drill six more production wells over the 2026–27 winter. Second, it would build a dedicated helium liquefaction and carbon dioxide (CO2) "Rare Gas Hub". Third, it is relying on Minnesota's new helium permitting regime. In July 2026 the company said it was targeting first helium in the fourth quarter of 2027. However, Pulsar (TSXV:PLSR) has stated that it has assigned no reserves and that no economic feasibility study yet supports the project. Funding and permits will therefore decide whether that timeline holds.

Listings and recent financing

Pulsar (TSXV:PLSR) is listed on the TSX Venture Exchange and on London's AIM market under the symbol PLSR. Its shares also trade on the US OTCQB as PSRHF. It reports in US dollars. In July 2026, the company raised about US$25.5 million gross through a placing, a subscription and a retail offer at 75 pence per share. According to its results announcement, that was equal to about C$1.43 per share. The deal issued about 25.4 million new shares, roughly 13.5 per cent of the Share Capital before the raise. That took total voting rights to about 214.1 million common shares.

Earlier in the fiscal year, Pulsar (TSXV:PLSR) raised about US$9.9 million through a private placement. It also received several million dollars from Warrant and option exercises. Pulsar's (TSXV:PLSR) fiscal year ends on 30 September. In its 1 October 2026 equipment announcement, the company said it had cash resources of US$25.2 million.

What the Topaz drilling has shown

Topaz sits near Babbitt in Minnesota's Lake County. The company drilled seven Jetstream wells, including five core-hole appraisal wells between October 2025 and March 2026, and each of those five hit high-pressure gas. Pulsar (TSXV:PLSR) has designated Jetstream #1 and #2 as production-ready. It has said Jetstream #3 to #7 were not designed or permitted for conversion to production. Earlier sampling at Jetstream #1 showed helium concentrations between 7.9 and 14.5 per cent, which is high by global standards. In January 2026, two US federal laboratories measured helium-3 at roughly 11.2 to 11.9 parts per billion in raw gas from that well.

Pulsar's (TSXV:PLSR) June 2026 project update said its land position includes about 690 net mineral acres owned outright with no production royalty, and about 4,941 net acres under gas leases. Interpretation of a 2D seismic survey was complete. The company was also building a combined geological model from well, seismic and airborne gravity data. CEO Thomas Abraham-James said at the time that "the hard work of the exploration phase is complete, now it is time to build."

The Rare Gas Hub and October milestones

The biggest recent developments concern processing. On 1 October 2026, Pulsar (TSXV:PLSR) said it had signed and accepted a firm equipment proposal from Chart Energy & Chemicals, which the release described as a Baker Hughes subsidiary. The equipment covers a helium purification and liquefaction plant with about 861 litres per hour of capacity, plus a CO2 plant designed to capture 300 tonnes per day. The total equipment price is about US$85.5 million, not including installation, site infrastructure, taxes and other costs. An upfront payment of about US$5.0 million was to come from existing cash. A second milestone payment of US$8.55 million is scheduled for 31 January 2027 and depends on further funding.

On 12 October, the Two Harbors city council approved a purchase and development agreement with Pulsar's (TSXV:PLSR) Minnesota Subsidiary for a 62-acre site. Under the agreement, the company would pay $1 for the land. The city would contribute up to $1 million toward rail, site clearing and utilities. Closing depends on an environmental review, financing and land-use approvals. On 14 October, Pulsar (TSXV:PLSR) signed an evaluation agreement with Lunar Helium-3 Mining to lab-test recovery of helium-3, an isotope used to cool many quantum computers. On 23 October, the US Department of Energy added helium to its Critical Material List, which Pulsar (TSXV:PLSR) welcomed in a statement.

Greenland and the wider portfolio

Outside Minnesota, Pulsar (TSXV:PLSR) owns all of the Tunu project in East Greenland. It holds an exclusive exploration licence covering about 62 square kilometres. Samples from thermal springs there have shown helium concentrations of up to 0.8 per cent, with no link to hydrocarbons. An independent pre-feasibility assessment by Sproule-ERCE pointed to potential for a combined geothermal power and helium development. That potential depends on further technical work. Tunu is still at the exploration stage, and no drilling schedule has been published. In 2026 Pulsar (TSXV:PLSR) also acquired Quantum Hydrogen and the company behind its Falcon helium project in Michigan's Upper Peninsula.

Risks to the production timeline

The plan faces several risks. The Chart equipment contract alone exceeds the company's reported cash, so Pulsar (TSXV:PLSR) will need debt, public-sector funding or more equity. More Equity would mean further dilution. If the January 2027 milestone payment is missed, the contract can go into a suspension period. Commercial production also depends on Minnesota finishing rulemaking, environmental review and permitting under its helium law, which was signed in May 2026. The company has said it has no gas-processing customers yet. Results from the planned production wells, including sustained flow rates, have not yet been reported. Helium prices also tend to be opaque and are often set through private contracts. Pulsar (TSXV:PLSR) reported a net loss of about US$12.2 million for the six months to 31 March 2026, which included a non-cash warrant Revaluation loss. This shows how much the company relies on capital markets.

Conclusion

Over the past six weeks, Pulsar Helium (TSXV:PLSR) has made progress on infrastructure at Topaz. It accepted an equipment contract, secured a potential plant site in Two Harbors, signed a helium-3 evaluation agreement and benefited from helium's new critical-material status in the US. The next markers to watch are the start and results of the six-well production drilling program and financing for the US$8.55 million January payment. Pulsar's (TSXV:PLSR) fiscal 2026 annual results are also due.