  • CCMI revises its restart application to combine underground mining and milling operations in one submission.
  • Engineering work underway with final permit application targeted for Q1 2026.
  • Sale of stockpiled ore supports permitting costs and reduces financial pressure.

Canadian Critical Minerals Inc. (TSXV: CCMI) (OTCQB: RIINF) mining company focused on copper, with full ownership of the Bull River Mine in B.C. and a 10% stake in XXIX Metal Corp., which owns the Thierry and Opemiska copper projects in Ontario and Quebec.

The company has announced a revised approach to its application to restart the Bull River Mine (BRM) near Cranbrook, British Columbia. Following discussions with the province’s Major Mines Permitting Office, the company will consolidate its previous two-phased plan into a single application that encompasses both underground mining and mill operations.

Previously, the company pursued a phased restart strategy. Phase one focused on processing an existing 180,000-tonne surface stockpile through BRM’s 700-tonne-per-day mill, with filtered tailings deposited at surface. Phase two aimed to resume underground mining and return tailings underground as cemented backfill. The revised application, if approved, would enable simultaneous commencement of underground mining and milling, streamlining the restart process.

Consultants have been engaged to support the updated submission. Moose Mountain Technical Services is preparing a detailed underground mine plan, expected to be completed by early August 2025. ALS Metallurgical Services is conducting additional humidity cell testing on planned tailings, building on prior testing programs to simulate long-term leaching behaviour. The results, along with past engineering work including a filtered tailings facility design by Stantec Engineering will be compiled into a Final Permit Application, targeted for submission in Q1 2026.

CCMI has already completed crushing and screening of the surface stockpile. Approximately 7,900 tonnes of pre-concentrated copper, gold, and silver material have been trucked to New Afton under an Ore Purchase Agreement (OPA). An additional 2,100 tonnes are expected to be delivered by August 2025. The remaining 170,000 tonnes of fines and rejects from the ore sorting process will remain on site and are expected to provide mill feed for roughly eight months after restart.

Proceeds from the OPA have enabled CCMI to reduce payables and cover care-and-maintenance costs, as well as funding permitting expenses without issuing new equity. This has supported progress on engineering studies in a more continuous manner. The BRM project includes over $100 million in infrastructure and is connected to grid power and an all-weather road network. The mine remains dewatered and accessible, with 22,000 metres of underground development reaching depths of 350 metres.

Company President and CEO Ian Berzins stated that combining the restart phases under one application will support a more efficient permitting process and potentially reduce the consultation burden on First Nations and regulators. The company continues to engage with government bodies to advance the project.