Highlights:

  • The Karowe Underground Project is expected to operate for approximately 10 years, mining 4.5 million carats.
  • Pre-production capital costs total 779M USD, with over 436M USD already spent on the project.
  • The project is projected to generate more than 1.3B USD in net income, with an NPV8% of 432.1M USD.

Lucara Diamond Corp. (TSX:LUC) has published an updated technical report for its Karowe Underground Project (UGP) in Botswana. The 2025 Feasibility Study (FS), prepared by JDS Energy & Mining Inc., revises previous assessments from the 2023 FS. The report provides updates on capital expenditure, project scheduling, mining technical solutions, and economic modeling. It will be available on SEDAR+ and the company’s website within 45 days.

Mine Life and Production Projections
The underground mine is planned to extend Karowe’s operational life by roughly 10 years. The project anticipates mining 28.5 million tonnes of ore and processing 37.3 million tonnes over the life of mine (LOM). Total diamond recoveries are estimated at 4.5 million carats, focusing on the South Lobe kimberlite, which remains open at depth. This area has historically produced large, high-value diamonds, including the 2,488-carat Motswedi, 1,109-carat Lesedi La Rona, 549-carat Sethunya, and more recently the 2,035-carat and 1,019-carat diamonds recovered in 2025.

Capital and Economic Details
Pre-production capital expenditure is projected at 779M USD, of which over 436M USD has already been spent. The remaining 343.2M USD is expected to be funded through operating cash flow and potential equity or debt financing. The underground project is forecasted to generate more than 1.3B USD in net income, with an after-tax unlevered NPV8% of 432.1M USD. Production is scheduled to commence in H1 2028, following completion of open-pit operations.

Technical and Operational Updates
The updated FS incorporates advancements in underground development, including completed production and ventilation shafts and lateral connections. The report also includes revised economic modeling, updated diamond pricing, inclusion of legacy stone values, and re-baselined schedules for mining and processing. Geological, hydrogeological, and geotechnical updates, along with detailed mine design and groundwater management strategies, are incorporated. The underground operation will process 2.85 million tonnes per annum using Long Hole Shrinkage mining methods, with ROM material transferred to surface via shafts, conveyors, and processing equipment.

Share performance
 LUC shares closed at CAD 0.20 on 5 January 2026.