Image source: © 2025 Krish Capital Pty.Ltd

Highlights

  • Company reports development progress, operating cost metrics, and targeted 2026 extraction approach.
  • 100 tpd mill identified; estimated CAD 1.0 million for acquisition and installation.
  • No feasibility study; notes historical production and cautions on production-decision risks.

Sixty North Gold Mining Ltd. (CSE: SXTY) (FSE: 2F40) (OTC Pink: SXNTF) released an operational update outlining recent development at the Mon Gold Mine and a staged plan to transition toward processing in 2026. The Company indicates it has focused recent months on financing options to support the shift from development to operations, alongside refining operating and capital cost estimates.

Since 2017, total investment at Mon stands at $6.2 million. This includes $2.6 million in acquisition costs and $3.6 million in exploration and development. Within that latter figure are $427,540 in recoverable reclamation bonds, approximately $900,000 allocated to mining and operations equipment, and about $2.2 million for development labour and consumables.

Development to date totals 226 metres, incorporating portal repairs, ramp slashing and advance, crosscuts, and services. The workings have accessed the A-Zone quartz veins below two historic stopes. Those historic stopes collectively extracted 15,000 tonnes of ore over 112 metres of strike and 15 metres of vertical extent at a reconciled grade of 30 g/t gold—about 1,000 ounces of gold per vertical metre (NI 43-101 Technical Report, August 3, 2023).

During the 2024 program, direct operating costs averaged approximately $10,000 per day or $4,800 per metre advanced, translating to roughly $143 per tonne of development rock. The operating team included two miners on a single shift plus a mine manager, geologist, mechanic, and support staff.

For 2026, the plan is to subdrift north and south along both limbs of the A-Zone for roughly 137 metres, positioned 16 metres and 18 metres below the East and West stopes, respectively. The Company intends to mine four stopes using a mechanized resue method to limit dilution—driving a 2.5 x 3.0 metre subdrift along the footwall, then slashing and removing the vein in full, with subsequent lifts using waste to backfill previously mined voids. Management targets recovering approximately 20,000 tonnes from the A-Zone in this phase, with per-tonne costs initially similar to prior levels and potential reductions as vein exposure increases.

A 100 tpd mill has been sourced for acquisition, freight, and installation in spring 2026 at an estimated capital cost near $1,000,000. An additional $344,564 in environmental bonding is required prior to commissioning. Full-scale operations would add a second two-person mining crew, two mill operators, two support staff, and an additional mechanic, increasing labour costs about 50% to ~$15,000 per day, with consumables (fuel and explosives) near $5,000 per day.