Apollo Silver at a glance
What is Apollo Silver Corp. (TSXV:APGO) working towards? As of 28 October 2026, the Vancouver-based explorer is trying to move its Calico Silver Project in San Bernardino County, California, from a large defined resource towards a first economic study, while also dealing with a community access question at its optioned Cinco de Mayo project in Chihuahua, Mexico. Calico is the company's main asset. A preliminary economic assessment (PEA) was started in March 2026 and was guided for the third quarter. Apollo's own news page listed no PEA results when it was checked for this article.
The shares trade on the TSX Venture Exchange under APGO, on the OTCQB as APGOF and in Frankfurt as 6ZF. Apollo was ranked 13th overall in the 2026 TSX Venture 50, but that is a performance ranking, not an index. This research found no dated constituent evidence placing the stock in the S&P/TSX Venture Composite Index or any other S&P/TSX index, so its index status is recorded as pending verification.
The Calico resource base
Calico's current mineral resource estimate was prepared by Stantec under NI 43-101. It was announced on 4 September 2025 with an effective date of 30 June 2025. At the Waterloo property it reports measured and indicated resources of 55 million tonnes at 71 grams per tonne silver, for about 125 million ounces. Of that, 104 million ounces are in the measured category. The adjacent Langtry property adds an inferred resource of 24 million tonnes at 73 g/t silver, or about 57 million ounces. Waterloo also carries indicated barite and zinc, plus a small inferred gold resource.
The estimate assumed prices of US$28 per ounce for silver, US$2,451 per ounce for gold, US$120 per tonne for barite and US$1.22 per pound for zinc. The company stresses that mineral resources are not mineral reserves and have no demonstrated economic viability. That caveat matters because no PEA, pre-feasibility study or feasibility study has yet been published to test the economics.
Barite and zinc are part of Apollo's pitch. The company calls both critical minerals for US energy, industrial and medical uses. In February 2026 it said it had been accepted into a US Defense Industrial Base consortium. The company does not produce any metal.
Developments during 2026
Much of 2026 has been about funding and leadership. In January Apollo closed a C$27.5 million private placement in two tranches. Jupiter Asset Management invested C$12.5 million and insiders took part with about C$2.36 million. On 18 March the company said it had started the Calico PEA. After the 27 March annual meeting, Tom Peregoodoff became executive chair.
Field results followed on 11 May. Selective surface samples assayed up to 1,280 g/t silver at the Mule property, up to 4.85 g/t gold and 30 per cent zinc at the Burcham target near Waterloo, and up to 76.12 per cent barite at Langtry. The company warned that selective samples may not represent the underlying mineralisation. In the same release it said final drilling permits were expected in the second quarter. A 4,500-metre large-diameter core programme for metallurgical and geotechnical work, plus about 1,000 metres testing Burcham's gold potential, would follow in the third quarter once summer heat had eased. This drilling is meant to support a later pre-feasibility study, not the PEA.
The management team then changed again. Ross McElroy stepped down as president, chief executive and director on 15 July 2026. Colin Sutherland, a chartered accountant with mining finance and operating experience in Mexico, took his place. On 1 September Steven Thomas, a former chief financial officer of Torex Gold and Mountain Province Diamonds, became CFO, replacing Chris Cairns.
The Cinco de Mayo question
The second asset brings a different kind of risk. Apollo holds an earn-in interest in Cinco de Mayo, a carbonate replacement deposit that the company describes as high-grade and large-tonnage. Historical drilling in 2012 at the Pegaso zone returned an intercept of 349 g/t silver equivalent over 61.60 metres.
Access depends on the local Ejido Benito Juárez, which has had a moratorium on mineral exploration and development affecting the project lands since 2012. An ejido assembly called for 20 September 2026 was adjourned, apparently for lack of quorum, before it considered lifting the moratorium and approving a long-term access agreement. Apollo said on 21 September that the assembly would reconvene, probably in October, and that a simple majority of those attending could decide at the second meeting. No definitive agreement had been disclosed when this research was done.
Funding, dividends and valuation
Apollo is a pre-revenue explorer, so spending depends on equity markets. The January placement is the most recent financing found. This research did not open the latest interim financial statements, so no current cash balance or quarterly loss is given here. Apollo pays no dividend, which is normal for a company at this stage.
Stockwatch data showed 63,182,799 shares in issue in mid-July. The shares closed at C$2.52 on 15 July 2026, giving a market value of about C$159 million, down from C$3.26 in early May. No current price was checked.
Industry drivers and principal risks
Silver prices, US interest in domestic supplies of critical minerals and investor appetite for development-stage projects are the main external factors. Calico's low-grade, bulk-tonnage profile makes the outcome sensitive to recoveries, by-product credits and capital costs. The resource work assumed silver recovery of only 65 per cent, so metallurgy is a central technical question.
Other risks include delays to the PEA and to drilling permits, both of which have already slipped. California permitting and desert operating conditions are further challenges. The company faces dilution from future financings and has had three senior leadership changes within a year. At Cinco de Mayo, the outcome of a community vote that the company cannot control will decide whether exploration can resume at all.
Milestones to watch
Apollo has pointed to several near-term catalysts. The most important is the delayed Calico PEA, which will give the first formal view of possible mine economics. The others are the start of the metallurgical, geotechnical and Burcham drilling, the reconvened ejido assembly on Cinco de Mayo, and any future financing. The evidence available on 28 October 2026 leaves those questions open.