Skeena Resources Limited (TSX:SKE), which now operates under the Brand Skeena Gold & Silver, is trying to do something relatively rare in Canadian mining: restart a famous past-producing mine on a much larger, open-pit scale. Its Eskay Creek project in northwest British Columbia's Golden Triangle was once described by the company as the highest-grade gold mine in the world. Skeena is now building a new operation there, with initial production targeted for the second quarter of 2027.

That is why the "bringing Eskay Creek back to life" framing fits. The project is fully permitted and under construction, and in April 2026 the company completed a US$750 million senior secured notes offering to help fund the remaining work and buy back part of a gold stream. Its most recent quarterly update, released on 13 August 2026, reiterated the Q2 2027 production target.

Skeena is a constituent of the S&P/TSX Composite Index, the broad benchmark of roughly 215 to 220 Canadian-listed companies. It is one of a small group of pre-production developers in the index, meaning its valuation rests largely on expectations for a mine that has not yet started operating. The shares also trade on the New York Stock Exchange under the same ticker.

A Legendary Mine With a Second Act

Eskay Creek sits about 250 kilometres from Stewart, British Columbia. According to Skeena, the original underground mine ran for 14 years, from 1994 to 2008, producing approximately 3.3 million ounces of gold and 160 million ounces of silver at average grades of 45 grams per tonne gold and 2,224 grams per tonne silver. The company says it ceased operating in 2008 because of unfavourable Commodity prices at the time.

Skeena optioned the property from Barrick Gold in 2017 and acquired full ownership in 2020 after exercising that option. Rather than reopening the old underground workings, the company plans an open-pit operation that targets lower-grade material surrounding and remaining from the historic mine, at much larger tonnages.

What the Feasibility Study Envisions

Skeena's 2023 definitive feasibility study, as summarised on the company's website, outlined a 12-year open-pit mine life. It projected average annual production over the first 10 years of 260,000 ounces of gold and 7.65 million ounces of silver, equivalent to about 370,000 gold-equivalent ounces. Reserve grades were put at 2.6 grams per tonne gold and 69 grams per tonne silver, or 3.6 grams per tonne gold equivalent. The study assumed US$1,800 per ounce gold and US$23 per ounce silver, well below spot prices in 2026, and presented all-in sustaining costs that Skeena says would place Eskay Creek among the lowest-cost open-pit precious metals mines globally.

These are study-based projections rather than operating results, and actual performance could differ once Mining begins. The silver by-product is a notable feature, giving the project exposure to both precious metals.

Construction Progress and a Higher Budget

On 31 March 2026, Skeena reported that Eskay Creek was 49% complete as of 28 February 2026. Process plant engineering was 92% complete and was forecast to finish in April 2026, procurement had 88% of costs committed, and process plant construction was 46% complete, with the concentrator building and critical-path concrete finished and mechanical installation underway. Across the whole project, 66% of costs were committed.

The same update showed that the budget has risen. Skeena put the total project budget at US$659 million, up from US$560 million in the 2023 study, with US$305 million invested through 31 December 2025 and US$354 million remaining to reach initial production. Environmental assessment and permitting milestones were achieved in February 2026, and the company says Tahltan values were incorporated into site requirements, with some arrangements forming part of its Impact Benefit Agreement commitments. In 2025, the Tahltan Nation voted to support that agreement.

Financing the Finish Line

On 10 April 2026, Skeena completed a US$750 million offering of 8.5% senior secured notes due 2031. According to the company, around US$184 million was used to repurchase 66.67% of a US$200 million gold stream held by Orion and its affiliates, about US$94 million prefunds 18 months of interest in a reserve account, and roughly US$470 million is for Eskay Creek construction, disbursements and general corporate purposes. The original stream entitled holders to 10.55% of payable gold at 10% of the Market Price for the life of the mine, so buying back two-thirds of it increases Skeena's retained exposure to gold prices.

The notes replaced the undrawn senior Loan and cost-overrun Facility elements of the 2024 financing package. While the refinancing simplifies the Capital Structure and removes part of the stream, an 8.5% coupon on US$750 million represents a significant interest burden for a company that is not yet producing.

Opportunities and Risks

The opportunity is straightforward to describe: if Eskay Creek is completed on schedule and performs close to the feasibility study, Skeena could move from developer to producer during a period of historically high gold and silver prices. The partial stream buyback means more of that upside would accrue to shareholders.

The risks are equally clear. Construction projects in remote northern British Columbia face weather, logistics and labour challenges, and the budget has already increased from the 2023 estimate. Start-up and ramp-up periods at new mines often take longer than planned. The new notes add Leverage and fixed interest costs, and the company's financial results currently reflect spending rather than revenue. Metal prices could also fall from current levels. Relationships with the Tahltan Nation and other Stakeholders remain important to the project's social licence.

What Investors May Watch Next

Key milestones include further construction progress updates, completion of mechanical installation at the process plant, pre-stripping and stockpiling ahead of commissioning, and the approach towards the Q2 2027 initial production target. Investors may also watch third-quarter 2026 financial results, any changes to the capital cost estimate, and management changes; at its June 2026 annual meeting, the company announced that Ryan Maloney had been appointed Vice President of Corporate Development.

Skeena (TSX:SKE) is in the final stretch of turning a historic mine into a modern operation. The next several quarters are likely to determine whether Eskay Creek's second life lives up to its first, and how the market values the company as it transitions to production.