Gold Production: Approximately 60,000 ounces in Q1 2025. Copper Production: 12 million pounds in Q1 2025. Cash Position: $608 million at the end of Q1 2025. Adjusted Net Earnings: $26 million or $0.13 per share in Q1 2025. Sales: Over 61,000 ounces of gold and 12.1 million pounds of copper in Q1 2025. Average Realized Gold Price: $2,554 per ounce in Q1 2025. Average Realized Copper Price: $3.80 per pound in Q1 2025. Molybdenum Sales: Approximately 4.2 million pounds at an average price of $21.59 per pound in Q1 2025. Consolidated All-In Sustaining Costs: $1,491 per ounce on a byproduct basis in Q1 2025. Free Cash Flow: $10 million in Q1 2025. Mount Milligan Cash Flow: $39 million from operations and $27 million in free cash flow in Q1 2025. Oksut Cash Flow: $50 million from operations and $42 million in free cash flow in Q1 2025. Share Buybacks: 2.5 million shares repurchased for $15 million in Q1 2025. Quarterly Dividend: CAD$0.07 per share declared.

Warning! GuruFocus has detected 3 Warning Sign with CGAU.

Release Date: May 06, 2025

For the complete transcript of the earnings call, please refer to the full earnings call transcript.

Positive Points

Centerra Gold Inc (NYSE:CGAU) generated positive free cash flow at both operations in the first quarter. The company maintained a strong cash position of $608 million, ensuring financial flexibility. Centerra Gold Inc (NYSE:CGAU) plans to repurchase up to $75 million of its shares in 2025, demonstrating a commitment to returning capital to shareholders. The updated resource at Kemess shows robust mineralization, with significant gold and copper resources. The company is advancing key growth initiatives, including the Mount Milligan PFS and Kemess PEA, which are expected to unlock significant value.

Negative Points

Gold and copper production in the first quarter was lower than planned due to lower grades at Mount Milligan and Oksut. All-in sustaining costs on a byproduct basis were higher compared to the last quarter, driven by increased costs and lower sales. The molybdenum business unit experienced a free cash flow deficit, mainly due to spending on the Thompson Creek restart. The company faces potential impacts from US tariffs on its operations, particularly at the Langeloth facility. There is uncertainty regarding the timeline and costs associated with the development of the Kemess project.

Q & A Highlights

Q: With the shift in mining method to long haul open stoping from block caving at Kemess, is it too early to provide any magnitude of development CapEx, or would you expect potential development of Kemess to be internally funded? A: Paul Tomory, President and CEO, explained that the previous block cave concept was shelved due to high development CapEx and low payable metal. The new approach involves an open pit combined with a conventional underground operation, which is expected to lower CapEx. Centerra intends to fund all development projects, including Kemess, with existing and future liquidity without accessing equity or debt markets.

Story Continues

Q: What synergies do you see with Thesis Gold's LawyersRanch project, and what infrastructure at Kemess could be leveraged? A: Paul Tomory noted that Kemess has significant infrastructure, including an airstrip, power line, and camp with a mill, which could be leveraged for broader development in the Toodoggone district. Centerra sees potential synergies with Thesis Gold's project, given the proximity and existing infrastructure.

Q: Does the inclusion of Kemess in the pipeline deprioritize the need for acquiring a new gold project? A: Paul Tomory confirmed that Kemess, with its built infrastructure and favorable attributes, reduces the need for M&A. Centerra is focusing on developing Kemess and the Mount Milligan extension, which are expected to provide significant future potential.

Q: Can you provide an update on the molybdenum business unit and the potential impact of tariffs? A: Ryan Snyder, CFO, stated that about 60% of feed for Langeloth comes from South America and is subject to tariffs. Centerra is exploring strategies to mitigate this impact. The company remains committed to the molybdenum business and sees strong demand from US customers.

Q: Could you provide an update on community relations at Kemess and the feasibility of an open pit? A: Paul Tomory explained that the new open pit concept is significantly smaller than the previous one, reducing environmental impact. Centerra maintains good relations with local communities and has an Impact Benefit Agreement in place, which supports the feasibility of the open pit.

For the complete transcript of the earnings call, please refer to the full earnings call transcript.

This article first appeared on GuruFocus.