Freeman Gold Corp. (TSXV: FMAN | OTCQB: FMANF | FSE: 3WU) announced on November 23, 2026 that its 100%-owned Lemhi Gold Project in Lemhi County, Idaho has been accepted as a "Covered Project" under the FAST-41 federal permitting framework. The designation, overseen by the Federal Permitting Improvement Steering Council, provides a publicly tracked, coordinated permitting timetable with multi-agency accountability. The milestone is significant for investors following the company's progress toward a construction decision on the feasibility-stage gold deposit.

Key Points

  • Freeman Gold Corp. (TSXV: FMAN | OTCQB: FMANF | FSE: 3WU) announced FAST-41 Covered Project status for the Lemhi Gold Project
  • The U.S. Forest Service will serve as lead agency; a Coordinated Project Plan is expected to be posted to the Federal Permitting Dashboard within 60 days
  • The 2026 Feasibility Study estimates an after-tax NPV(5%) of US$696 million, IRR of 34.4%, and initial capital cost of US$329.7 million at a base-case gold price of US$3,650/oz
  • Investors may watch for submission of the Mine Plan of Operations, targeted for December 2026

What FAST-41 Covered Status Means for Lemhi Permitting

Freeman submitted its FAST-41 Initiation Notice on November 6, 2026. The Lemhi Project qualified under the standard eligibility pathway: mining is an eligible sector under FAST-41, the project requires National Environmental Policy Act review, and its estimated initial capital cost of US$329.7 million exceeds the US$200 million eligibility threshold. As a Covered Project, federal environmental reviews will follow a single coordinated timetable published on the Federal Permitting Dashboard, with the Permitting Council monitoring progress and cooperating agencies working alongside the U.S. Forest Service.

Idaho State Permitting Aligned With Federal Timeline

Under a memorandum of understanding signed on February 19, 2026, between the State of Idaho and the Federal Permitting Improvement Steering Council, Idaho state permitting actions for Covered Projects are coordinated with federal timelines and tracked on the Federal Permitting Dashboard. The release states this arrangement is intended to reduce duplicative reviews. Environmental baseline studies covering water, air, soil, geochemistry, land use, and socioeconomics are underway, led by GSI Environmental Inc. as the company's permitting consultant.

Lemhi Feasibility Study Economics Supporting the Permitting Push

The 2026 Feasibility Study underpins Freeman's permitting advancement, outlining a conventional open-pit, carbon-in-leach operation with Proven and Probable Mineral Reserves of 43.04 million tonnes at 0.74 g/t gold for approximately 1.03 million ounces. At the base-case gold price of US$3,650 per ounce, the study estimates an after-tax NPV(5%) of US$696 million, an after-tax IRR of 34.4%, a 2.5-year payback, a 15.2-year mine life, average annual production of approximately 75,100 ounces over the first ten years, and a life-of-mine all-in sustaining cost of US$1,719 per ounce.