Cameco (TSX:CCO) and Denison Mines (TSX:DML) have lagged the strength in uranium contract prices because the benefits of higher prices reach their results slowly. Cameco sells most of its uranium under long-term contracts with price ceilings, and its third quarter was hurt by a longer planned shutdown at its Key Lake mill, leading to an adjusted net loss. Denison, meanwhile, is still building its Phoenix mine, with first production targeted for mid-2028, so it has almost no Revenue today.
Broader resource-sector selling in November has added pressure to both stocks.
What did Cameco report for the third quarter?
Cameco reported third-quarter revenue of C$619 million, up 1% from C$615 million a year earlier, and net Earnings of C$43 million, or C$0.10 per share. On an adjusted basis, it posted a net loss of C$2 million, compared with adjusted earnings of C$32 million a year earlier, missing analyst expectations. Adjusted EBITDA fell 14% to C$267 million, and Gross Profit fell 28% to C$122 million.
Uranium production fell 20% to 3.5 million pounds, and the cash cost per pound mined rose 62% to C$40.73. Cameco delivered 5.6 million pounds at an average realized price of US$91.76 per pound. The shares fell about 9% on October 30, the day of the release.
Why didn't Cameco benefit more from higher prices?
Cameco's contracts include price ceilings and fixed elements designed to protect it when prices fall, but they also limit gains when prices rise. Based on the company's own sensitivity table, a hypothetical US$160 Spot Price would translate into an average realized price of only about US$69 per pound in 2026. If uranium stayed at US$100, management estimates realized prices would rise to about US$73 in 2027 and US$80 in 2028, as contract terms step up.
Cameco has commitments to deliver an average of about 28 million pounds a year from 2026 to 2030, with higher volumes in the early years.
What guidance changes did Cameco make?
Cameco narrowed its 2026 uranium production guidance to 19.5 million to 20.5 million pounds, from 19.5 million to 21.5 million, and delivery guidance to 29.5 million to 30.5 million pounds, from 29 million to 32 million. It raised expected average unit costs and administrative costs, and lowered Capital spending guidance because some work moved into 2027. The board declared an annual Dividend of C$0.24 per share, payable December 15 to shareholders of record on November 30.
How did Westinghouse perform?
Cameco owns 49% of Westinghouse Electric, the nuclear reactor and services company. Its share of Westinghouse's adjusted EBITDA rose 15% to C$143 million in the quarter, while its share of net loss improved to C$24 million from C$32 million. Year-to-date Westinghouse EBITDA was lower because the 2025 period included a large payment tied to the Dukovany reactor project in the Czech Republic. Westinghouse gives Cameco exposure to new reactor construction and fuel services beyond mining.
Where does Denison's Phoenix project stand?
Denison began full-scale construction of its Phoenix in-situ recovery (ISR) uranium mine at the Wheeler River property in northern Saskatchewan in July 2026, after receiving a construction licence from the Canadian Nuclear Safety Commission in February. Phoenix is the first new uranium mine in Canada to receive federal construction approval in more than 20 years. Denison expects initial capital spending of about C$600 million and production of about 56.2 million pounds over an initial 10-year mine life.
The company has installed camp facilities for nearly 400 people and started freeze wall installation, which creates a frozen underground barrier to contain the Mining solution. First production is targeted for mid-2028.
Why are uranium stocks volatile right now?
Long-term uranium contract prices have been at nominal record highs, while utilities are still signing contracts below the levels needed to replace what they consume, according to industry commentary. Supply problems at major producers, including Kazatomprom's sulphuric acid issues, add to tightness. However, uranium shares have also been caught up in broader selling of resource stocks and AI-linked power names. Cameco fell 4.74% on November 2 amid sector-wide pressure, and the TSX materials sector has been volatile.
How do the two companies differ for investors?
Cameco is a large, producing company with mines, a mill, refining and conversion facilities, and a stake in Westinghouse, giving it diversified exposure to nuclear power. Denison is a developer whose value depends on building Phoenix on time and budget and then selling uranium at good prices. Denison carries more project risk but more direct exposure to uranium price changes once production starts.
What are the key risks?
For Cameco, the risks include operational issues at Key Lake and McArthur River, contract terms that cap gains, Westinghouse project performance and currency swings. For Denison, they include construction delays, cost overruns, the novel use of ISR mining in the Athabasca Basin, and financing. Both face uranium price volatility, policy changes and sentiment toward nuclear power.
What should investors watch next?
For Cameco, the key dates are its fourth-quarter results and 2027 production guidance in February, plus updates on the Key Lake restart and Westinghouse reactor projects. For Denison, investors will follow construction progress at Phoenix, uranium sales contract announcements and any change to the capital estimate. Utility contracting activity and term price indicators will matter for both.
Conclusion
Cameco and Denison are lagging record uranium contract prices because Cameco's contracts deliver higher prices gradually and its third quarter was hit by the Key Lake outage, while Denison will not produce until 2028. The long-term Demand story for nuclear power remains intact. Cameco's 2027 production guidance in February and Denison's construction milestones are the next major catalysts.