Americas Gold and Silver Corporation (TSX: USA | NYSE American: USAS) reported consolidated net revenue of $46 million for the second quarter ended June 30, 2026, a 71% increase compared to $27.0 million in Q2-2025, driven primarily by higher realised silver prices. Year-to-date revenues reached $114 million, representing a 126% increase over the first half of 2025, and nearly matching the company's entire fiscal 2025 revenue in six months. The quarter was marked by the completion of Phase 2 of the Galena No. 3 Shaft modernisation program and strong operational performance at the Cosalá Operations in Mexico, though silver production was temporarily affected by an electrical fire at Galena in June.
Key Points
- Americas Gold and Silver Corporation (TSX: USA | NYSE American: USAS)
- Q2-2026 consolidated net revenue rose 71% year-over-year to $46 million; year-to-date revenues of $114 million up 126% versus H1-2025
- Consolidated silver production of 665,000 ounces in Q2-2026; full-year 2026 guidance maintained at 3.2–3.6 million ounces at AISC of $30–$35 per ounce sold
- Investors may be watching production ramp-up at Galena in H2-2026 following shaft upgrade completion and resolution of the electrical fire impact
Cosalá Operations Deliver 26% Silver Production Increase on Higher Grades at EC120
The Cosalá Operations in Sinaloa, Mexico produced approximately 337,000 ounces of silver in Q2-2026, a 26% year-over-year increase compared to approximately 269,000 ounces in Q2-2025. The company attributed the improvement to higher silver grades and recoveries following the declaration of commercial production at EC120 effective January 1, 2026. Cash costs per silver ounce sold at Cosalá fell sharply to $16.91 per ounce from $30.61 per ounce in Q2-2025, reflecting higher by-product credits from copper and strong operational execution. Mining at the San Rafael Main Central orebody has ceased, with activity now concentrated in the higher-grade silver Upper Zone and EC120.
Galena No. 3 Shaft Modernisation Doubles Hoisting Capacity After Two-Phase Program
The completion of Phase 2 of the Galena No. 3 Shaft modernisation increased hoisting throughput from roughly 42 short tons per hour to sustained rates of 85 short tons per hour, with peak performance reaching 105 short tons per hour — a 150% improvement. The upgraded shaft is expected to deliver 1,350 tons per day of hoisting capacity. The Phase 2 investment totalled approximately US$1.1 million. Galena produced approximately 328,000 ounces of silver in Q2-2026, down from approximately 420,000 ounces in Q2-2025, as the planned shutdown and a minor electrical fire in June deferred access to a higher-grade stope into Q3-2026.
Debt Settlement and Balance Sheet Position Following Sprott and Royal Gold Transactions
During Q2-2026, Americas settled approximately $76 million of variable silver and gold delivery obligations with Eric Sprott and Royal Gold Inc. The Sprott obligation was settled on May 20, 2026 through the issuance of 7,956,696 common shares, while the Royal Gold obligation was settled on June 10, 2026 through delivery of 5,000 ounces of gold and the issuance of 2,652,532 common shares. The company reported cash and cash equivalents of $88.9 million and working capital of $48.6 million as at June 30, 2026. The settlements eliminate ongoing mark-to-market valuation impacts on the income statement going forward.