BCM Resources Corporation (TSXV: B) has announced that an aggressive geophysical survey programme is underway at its 100%-controlled Thompson Knolls porphyry-skarn discovery in Utah. Contractor Zonge International, Inc. has initiated ground-induced polarization and magnetotellurics surveys across the property, while a new drill hole, TK21, is also advancing. The combined activity signals a significant step-up in exploration pace at the copper, gold, silver, and molybdenum project, which investors may be watching closely following recent drilling results.
Key Points
- BCM Resources Corporation (TSXV: B) is a Vancouver-based mineral exploration company focused on its Thompson Knolls project in Utah
- Zonge International has commenced IP and magnetotellurics surveys expected to be completed in approximately 11 days, weather permitting
- New drill hole TK21 is advancing through fanglomerate cover, targeting a minimum depth of 4,000 ft (1,219 m) to test the western extension of the mineralising system
- Investors will be watching for assay results from recently completed hole TK20, with core expected to be delivered to the laboratory within the next few weeks
Zonge International Launches IP and Magnetotellurics Surveys at Thompson Knolls
BCM Resources has engaged Zonge International, Inc. of Reno, Nevada, to conduct systematic ground-induced polarization and magnetotellurics surveys at Thompson Knolls. Zonge's field crew is on site laying out survey lines, and the contractor has been engaged to deliver all IP and MT data acquisition services, 2D inversions, and a full acquisition and processing report with interpretations. The survey is expected to conclude in approximately 11 days, subject to favourable weather. The release states the surveys are intended to improve understanding of the subsurface expression of the large porphyry-skarn complex identified at the project.
TK21 Drill Hole Tests Western Extension of the Thompson Knolls Mineralising System
Drilling of hole TK21 is now underway, with the hole currently advancing through fanglomerate cover rocks. The company anticipates bedrock will be encountered at approximately 1,600 ft (488 m) depth, and BCM plans to extend the hole to at least 4,000 ft (1,219 m) to adequately test the vertical extent of the mineralising system. The release identifies TK21 as testing the western extension of the system, building on what the company described as a long mineralised intercept recorded in previously drilled hole TK20. The company did not disclose assay results from TK20 in this announcement.
Flooding Disrupted Access but Drilling Operations Have Resumed at the Utah Site
Recent flooding in the Thompson Knolls area created access challenges, slowing drilling activity for a few days. Significant precipitation caused overflow from the water reservoir at the project entrance and partially flooded a segment of main access Road 1700. The release states that drillers worked to lower the reservoir water level, exposing the original road track and enabling the resumption of heavy shipments. Bureau of Land Management-approved detour routes also allowed operations to continue. Core sawing of hole TK20 is accelerating with the addition of a second core-cutting shift, with remaining core expected at the laboratory within weeks.