Nord Precious Metals Mining Inc. (TSXV: NTH) has released an updated Mineral Resource Estimate for its Gowganda Silver Tailings Project in Ontario, confirming an Indicated Mineral Resource of 1,845,000 tonnes grading 47.4 grams per tonne silver and containing 2,814,000 ounces of silver at a 10 g/t cut-off grade. The estimate, prepared by independent firm GeoVector Management Inc. with an effective date of August 1, 2026, is intended to anchor engineering, metallurgy, and permitting work toward a silver-recovery development decision. Investors may be watching this update as Nord positions the surface-accessible tailings as the foundation for a recovery business and broader exploration programme.

Key Points

  • Nord Precious Metals Mining Inc. (TSXV: NTH, OTCQB: NPMMF, FSE: QN3)
  • Updated Gowganda Tailings MRE confirms 2,814,000 ounces of silver in the Indicated category across four domains at 47.4 g/t
  • A supporting NI 43-101 technical report will be made publicly available within 45 days of this announcement, or earlier if required by law
  • Investors should watch for new metallurgical study results and progress on the Mineral Recovery Permit application

Four Tailings Domains Define the Gowganda Silver Inventory

The updated estimate covers the Main Tailings, South Tailings, and two outflow domains. The Main Tailings account for the largest portion, contributing 1,762,000 tonnes at 46.3 g/t silver for 2,622,000 contained ounces. The South Tailings add 52,000 tonnes at 42.9 g/t, while Outflow One and Outflow Two contribute higher-grade but smaller volumes at 96.5 g/t and 134.0 g/t respectively. GeoVector used inverse distance squared interpolation of 1.5-metre composites and a block model with blocks measuring 3 metres by 3 metres by 1 metre. The Lower Bonsall area was excluded from the reported resource due to a flowing stream and revegetation.

Metallurgical Testing and Permitting Work Advance in Parallel

The cut-off grade assumption incorporates an 81.6% overall silver recovery drawn from a 2007 historical laboratory programme conducted by Met-Solve, which reported silver extraction of up to 82% using sodium thiosulphate. The release states that Nord is pursuing new metallurgical studies that may adopt a different processing method. Okane has begun technical reviews supporting a planned Mineral Recovery Permit application, and Nord has requested a separate proposal covering concurrent water-taking and environmental approval planning. The release notes these results will guide process selection, engineering, water management, and economic evaluation.

TTL Processing Capability and Broader Camp Strategy Underpin the Recovery Model

Nord's recovery strategy is supported by its wholly owned TTL Laboratories in Cobalt, described in the announcement as the only permitted high-grade milling facility in Ontario's historic Cobalt Camp. The company has also reported historical tailings work at its Castle and Beaver Mine sites. The release states Nord's longer-term aim is to develop a sequence of silver-recovery and rehabilitation projects drawing on TTL's processing infrastructure. The resource estimate and preliminary work do not establish economic viability or a decision to proceed with production, the disclosure notes.