Steppe Gold Ltd. (TSX: STGO) announced its financial results for the three and nine months ended September 30, 2026, reporting a sharp rise in revenue, profit, and operating cash flow driven by higher gold production, increased sales volumes, and elevated realised gold prices. Net profit attributable to shareholders reached $37.4 million in the quarter, more than five times the $7.1 million reported in the same period in 2025. The results also reflect the resumption of mining at the ATO Gold Mine and the company's first delivery under its amended stream agreement with Triple Flag International Ltd. Investors may be watching the company's progress on the ATO Phase 2 Expansion and its ability to secure financing for that project.

Key Points

  • Steppe Gold Ltd. (TSX: STGO | OTCQX: STPGF | FSE: 2J9) is a Mongolia-focused precious metals producer and developer.
  • Q3 2026 revenue rose to $86.6 million from $29.4 million in Q3 2025, with 19,984 ounces of gold sold in the quarter.
  • Average realised gold price was $4,319 per ounce in Q3 2026, compared to $3,412 per ounce in Q3 2025; full-year 2026 production guidance maintained at approximately 68,000 ounces.
  • Investors may be watching the revised ATO Phase 2 feasibility study, expected in Q4 2026, and progress on securing project financing.

Steppe Gold Q3 2026 Revenue, Profit, and Cash Flow Performance

Revenue for the third quarter reached $86.6 million, nearly triple the $29.4 million recorded in Q3 2025, with the company citing higher gold sales volumes and a rising average realised price of $4,319 per ounce. Adjusted EBITDA climbed to $56.4 million from $17.2 million in the prior-year quarter. Net cash generated from operating activities was $44.9 million for Q3 2026, compared with $9.0 million in Q3 2025. For the nine months ended September 30, 2026, revenue totalled $201.6 million and Adjusted EBITDA reached $141.2 million, reflecting broad-based improvement across the business relative to the same period in 2025.

ATO Gold Mine Resumes Operations and Throughput Metrics

The release states that mining activities resumed at the ATO Gold Mine during the quarter, with waste stripping commencing in August 2026 and ore mining beginning in September 2026. Across the group, 491,070 tonnes were milled and 481,821 tonnes were leached during the quarter. Mill recovery improved to 70% from 55% in the comparable 2025 period, while mill grade was 1.14 grams per tonne. The company produced 17,543 ounces of gold in Q3 2026, up from 14,722 ounces in Q3 2025, and retained 7,508 ounces of finished gold inventory at September 30, 2026 as part of its inventory management strategy.

Debt Management and Triple Flag Stream Obligations

During the nine-month period, Steppe Gold fully repaid the $14.3 million BORO bond and the TDB Gold II loan, and repaid $4.0 million of the MIK loan. The ATO Phase 2 loan repayment schedule was amended on August 7, 2026, deferring $49.6 million in outstanding principal to five instalments between March and August 2028. The company satisfied its first quarterly delivery obligation under the Triple Flag stream agreement on August 14, 2026, and subsequently settled its second quarterly obligation on November 13, 2026, each comprising metal credits equivalent to 1,250 ounces of gold.

ATO Phase 2 Expansion Advances Under Revised EPC Agreement

Steppe Gold continued engineering, procurement, and construction activities under an amended EPC agreement with Hexagon Engineering LLC, which carries a total contract value of approximately $238.2 million. The company advanced $21.4 million under the EPC agreement and paid $21.3 million in mining equipment deposits during the nine-month period. Land permitting approval has been received, and work on the overhead power transmission line and water exploration activities is underway. The revised feasibility study for ATO Phase 2 is expected to be completed in Q4 2026, with further advancement subject to financing availability, permitting, and satisfactory study review.