Key Highlights

  • Free Cash Flow and adjusted EBITDA are non-GAAP measures, reconciled to GAAP in the release.
  • For the quarter, orders reached $24.2bn, up 88% organically, and Revenue rose 22% to $11.1bn, or 12% organically.
  • Electrification orders rose 66% organically to $6.3bn, revenue climbed 68% to $3.6bn and Margin reached 18.4%.
  • GE Vernova is scheduled to report third-quarter 2026 results in a webcast on October 28, 2026 at 7:30am EDT.

GE Vernova (NYSE:GEV) raised its 2026 outlook on July 22, 2026 because orders, pricing and cash collection in its gas power and electrification businesses ran well ahead of plan. The company lifted full-year revenue guidance to $45.5bn to $46.5bn, from $44.5bn to $45.5bn, and raised free cash flow guidance to $11.5bn to $12.5bn, from $6.5bn to $7.5bn.

The adjusted EBITDA margin outlook of 12% to 14% was left unchanged. Free cash flow and adjusted EBITDA are non-GAAP measures, reconciled to GAAP in the release.

What The Business Does

GE Vernova, listed on the New York Stock Exchange under the ticker GEV, makes and services equipment that generates, transmits and manages electricity. It reports three segments: Power, which includes gas turbines, nuclear and hydro; Wind, covering onshore and offshore turbines; and Electrification, which spans grid equipment, transformers and software.

The company reports in US dollars and uses a calendar fiscal year, so its second quarter covers April to June 2026.

Reported Second-Quarter Figures

For the quarter, orders reached $24.2bn, up 88% organically, and revenue rose 22% to $11.1bn, or 12% organically. On a GAAP basis, Net Income was $0.6bn, a 5.8% margin, and Diluted Earnings per Share were $2.47, up 33% year on year.

Adjusted EBITDA was $1.25bn, an 11.3% margin. Operating Cash Flow was $5.5bn and free cash flow was $5.1bn, which the company said exceeded its full-year 2025 total. Cash stood at $13.1bn and total Backlog at $176bn.

Segment Picture

Power drove the quarter. Its orders rose 134% organically to $16.7bn, revenue grew 14% to $5.5bn and segment EBITDA margin improved by 240 basis points to 18.8%. The company said its gas power equipment backlog and slot reservations grew from 100 GW to 116 GW, with a target of at least 125 GW by the end of 2026.

Electrification orders rose 66% organically to $6.3bn, revenue climbed 68% to $3.6bn and margin reached 18.4%. The completed Prolec GE transformer Acquisition contributes roughly $3.1bn to the segment's 2026 revenue guidance, which flatters reported growth. Data Center orders exceeded $5bn in the first half, more than double the 2025 total.

Wind was the weak spot. Orders fell 40% organically to $1.2bn, revenue declined 10% to $2.0bn and segment EBITDA margin was negative 13.6%, down 630 basis points.

Sector Context

Across producer manufacturing, electricity equipment makers are benefiting from rising power Demand linked to data centers and grid upgrades. GE Vernova plans gas turbine output of 20 GW in the third quarter of 2026, 24 GW in 2028 and a 30 GW target for 2030, indicating capacity rather than demand is the near-term constraint.

Capital Returns

The company returned $3.9bn to shareholders through Buybacks and dividends in the first half. It repurchased 2.5 million shares for $2.3bn in the second quarter. On May 19, 2026 the board declared a $0.50 quarterly dividend, paid on July 14 to holders of record on June 16.

What the figures imply

The free cash flow upgrade is the more telling change, because it reflects customers paying deposits to secure turbine slots. That strengthens near-term Liquidity but may pull cash forward from later years. The unchanged margin range suggests Wind losses and integration costs continue to offset gains elsewhere.

Risks To Watch

Key risks include execution on a very large backlog, Supply chain and labor constraints as production ramps, continued Wind losses, integration of Prolec GE, Tariff and policy changes affecting renewables, and the possibility that data center demand grows more slowly than customers expect.

October 28 Webcast Tests the Backlog and Guidance

GE Vernova is scheduled to report third-quarter 2026 results in a webcast on October 28, 2026 at 7:30am EDT. Points to watch include the 125 GW backlog target and Wind margins.