Highlights

  • Ore supply resumed mid-July, with mill operations now running at full capacity.
  • Senegal pilot plant construction progressing on schedule, with modular plant delivery set for Q4.
  • Ecuador Svetlana plant acquisition advancing with corporate setup and environmental planning underway.

Dynacor Group Inc. (TSX: DNG) has provided a comprehensive corporate update, detailing operational progress and expansion initiatives in West Africa and Latin America. Following the lifting of road blockades in mid-July, ore supply to the mill resumed, allowing operations to run at full capacity. Dynacor’s focus remains on meeting guidance targets by maximising production, advancing purchasing activities, and implementing mill optimization projects.

Since the implementation of the new optimization initiatives, the Corporation has observed measurable improvements in mill efficiency and productivity. These measures include reduced reagent consumption, refined management processes, enhanced laboratory and water usage, and tailings pond optimization. Management noted that, “Supported by its reinforced operations and experienced teams, Dynacor is well-positioned to drive a stronger second half.”

Expansion Efforts in Key Regions

In Senegal, construction of a pilot plant is proceeding on schedule. Mobilisation of the construction team has begun, with work on access roads, land clearance, and fencing planned to start post-rainy season in September. Tailings pond construction is scheduled for late September, and the modular pilot plant is expected to be delivered in Q4 2025, targeting first ore production in Q1 2026.

In Ecuador, the Corporation’s acquisition of the Svetlana processing plant in July has initiated corporate structuring, plant upgrade planning, and local awareness-building. Dynacor is engaging with Ecuador’s Ministry of Production, Foreign Trade, Investment and Fisheries to finalise an Investment Protection Agreement, which provides legal, fiscal, and regulatory stability. The plant upgrade process is advancing, focusing on assessing the active tailings pond, safely decommissioning historic ponds, and reviewing the main electrical substation to support large motor commissioning. Retention of most plant personnel has enabled knowledge transfer and improved operational readiness. Community engagement for the Environmental Impact Assessment (EIA) supplementary study is set to commence following government approval. Management stated, “Given the absence of community dialogue since plant closure, the Corporation is looking forward to the opportunity to introduce Dynacor, its focus on fostering shared value with local stakeholders, and its track record of responsible environmental stewardship.”

In Ghana, discussions continue with the government following productive meetings in July. In Côte d’Ivoire, Dynacor is monitoring mining code revisions, though no decisions are expected before the presidential election in October.

The Corporation maintains its long-term target of generating more than US$1 billion in sales by 2030, reflecting a multi-regional expansion strategy combined with operational enhancements.