Giyani Metals Corp (TSXV:EMM) has filed the Definitive Feasibility Study (DFS) for its K.Hill battery-grade manganese project in Botswana, the technical milestone that anchors the company's pitch to lenders and offtakers and moves the developer a decisive step closer to a construction decision.
The study, filed on SEDAR+ on July 10, 2026, carries the headline results the company first disclosed on May 28: a post-tax net present value of US$481.5 million at an 8% discount rate and a post-tax internal rate of return of 20.3%. Those figures, unchanged between the two disclosures, now sit inside a full technical report that potential financiers and strategic partners can scrutinise.
For a junior developer whose value rests almost entirely on a single asset, the DFS is the document that turns a resource and a demonstration plant into a bankable proposition. It defines the Capital bill, the production profile and the price assumptions against which the entire Investment case will be judged.
The 2026 Catalyst
The DFS frames K.Hill as a 25-year operation. It carries an initial capital cost of US$535 million, including a US$55 million contingency, and a payback period of 4.8 years measured from the start of processing on an undiscounted basis. The plant is designed to process ore at a steady-state rate of about 220,000 tonnes per year.
Over the life of the project, the study models production of roughly 1,504 kilotonnes of high-purity manganese sulphate monohydrate (HPMSM) and a further 99 kilotonnes of high-purity manganese oxide (HPMO). Total life-of-project operating costs are put at US$2,781 million, with unit costs ranging from about US$1,300 to US$1,500 per tonne of HPMSM equivalent in the early years, rising to between US$1,580 and US$1,890 per tonne later in the mine life.
Those Economics rest on price assumptions that matter as much as any engineering input. The base case uses an average realised HPMSM price of US$3,220 per tonne and an average HPMO price of US$4,004 per tonne. The HPMSM price trajectory rises from US$2,700 per tonne in 2026 toward US$3,300 by 2031 before stabilising near US$3,200 over the long term. On those assumptions, the study generates total HPMSM Revenue of US$4,856 million and HPMO revenue of US$395 million across the life of the project, with a modelled start date of April 1, 2027.
Why It Matters
Manganese is a workhorse metal, but the battery-grade sulphate that Giyani is targeting is a far narrower product. HPMSM is a precursor chemical used in the cathodes of nickel-manganese-cobalt (NMC) lithium-ion batteries that power electric vehicles. Producing it to the purity that cathode makers Demand is a chemical-processing challenge, not merely a Mining one.
The strategic hook is geography. Refining of battery-grade manganese sulphate is overwhelmingly concentrated in China, leaving Western automakers and cell manufacturers exposed to a single-country Supply chain for a critical input. That concentration is precisely what Giyani is positioning against. A non-Chinese source of qualified HPMSM is the pitch that has drawn interest from US policy-linked finance, and it is the reason a Botswana developer with a modest Market Value is attracting attention from institutions focused on supply-chain resilience.
The Bigger Picture
K.Hill was granted its mining licence in September 2024, clearing a foundational permitting hurdle. Giyani has since worked to de-risk the flowsheet through a demonstration plant, producing first battery-grade manganese in March 2025 and shipping material to potential offtakers in May 2025 for qualification. Phase 2 interim results from the demonstration plant followed in May 2026, feeding operating data on reagent consumption and crystalliser management into the DFS.
On financing, the company has assembled a patchwork rather than a single facility. In June 2025 it received a non-binding letter of interest from the Export-Import Bank of the United States (EXIM) for up to US$225 million in long-term debt, with a repayment period of up to 15 years, under EXIM's Supply Chain Resilience Initiative. That interest is contingent on due diligence, final terms, completion of the DFS and, critically, securing offtake with US companies. Separately, South Africa's Industrial Development Corporation (IDC) has provided project-level Loan funding, drawing down a further ZAR29.9 million in March 2026 and lifting its combined facilities toward a ceiling of ZAR329.9 million.
Financial and Operational Position
Giyani is a pre-revenue developer. It generates no Operating Income from K.Hill, which remains in the study-and-permitting phase, and its Balance Sheet has been sustained through Equity raises and project-level debt. In 2025 the company closed an upsized private Placement for gross proceeds of C$3,569,622, earmarked for general Working Capital and to carry it through the demonstration-plant and DFS milestones.
That funding scale should be read against the US$535 million initial capital requirement identified in the DFS. The gap between the company's current resources and the capital needed to build K.Hill is the defining feature of its financial position, and closing it is the central task ahead.
What Could Move the Stock Next
With the DFS filed, attention shifts to the money. Conversion of the EXIM letter of interest into a binding commitment, or the signing of binding offtake agreements with US or Western cathode and cell makers, would be the most material catalysts, since EXIM support is explicitly tied to US offtake. Progress on a broader project-finance package, additional IDC support, or a strategic investor taking a position would each speak to the financeability the DFS is meant to demonstrate, while a formal construction decision would mark the transition from developer to builder.
Risks to Watch
The risks are commensurate with the opportunity. Financing scale is the first: raising US$535 million is a heavy lift for a company of Giyani's size, and any package is likely to be dilutive, debt-laden, or both. Second is price. The DFS economics lean on HPMSM prices near US$3,200 per tonne; a softer battery-metals market or slower EV demand would erode the NPV directly. Third is jurisdiction. While Botswana is comparatively stable and the mining licence is in hand, cross-border execution spanning Botswana operations and South African funding adds currency, counterparty and delivery risk. Demonstration-scale success also does not guarantee commercial-scale performance.
Conclusion
The K.Hill DFS gives Giyani a defined, filed and reasonably robust technical case: a 25-year mine life, a US$482 million post-tax NPV and a 20.3% IRR, underpinned by a demonstration plant that has already produced battery-grade material. What it does not yet give the company is the capital to build. The distance between a completed feasibility study and a funded construction decision is where the investment case will be won or lost, and financing and offtake milestones are the signals to watch from here.