Blossom Gold Inc. (TSX:BGAU) is running a 24,000-metre drilling programme at the Rosebud project in Pershing County, Nevada. The aim is to turn a former high-grade underground mine into an open-pit, heap-leach gold project. By 12 August 2026 the company had completed 13,991 metres, or about 58% of the programme, using four core rigs, and had secured a reverse-circulation rig. Recent results include 115.4 metres at 0.553 g/t gold in hole BG26-030 and 28.0 metres at 1.682 g/t gold in hole BG26-027.

Blossom Gold is one of the Toronto Stock Exchange's newest Mining issuers. It went public through a reverse Takeover that closed on 29 January 2026, alongside a C$115 million financing, and listed directly on the TSX on 2 February 2026 under the ticker BGAU. Since then, the company has focused on drilling, metallurgical testing and reopening underground access at Rosebud.

Company overview

Blossom Gold is based in Toronto and was formerly 1290448 B.C. Ltd. Rick Winters is Chief Executive Officer, and Dr John DeDecker leads exploration as Vice President, Exploration. The company has also appointed Alan Haslam as Vice President, Permitting, reflecting its plan to move Rosebud through technical studies towards development.

How it came to the TSX

The listing followed a reverse takeover in which 1290448 B.C. Ltd. combined with Investmin Resources. The deal closed on 29 January 2026, together with a C$115 million financing through subscription receipts priced at C$1.00. Rather than listing first on a venture exchange, Blossom Gold began trading directly on the TSX on 2 February 2026. The financing gave the company a substantial budget for drilling and study work from its first day as a public company.

The Rosebud project

Rosebud was mined underground from 1997 to 2000 by Rosebud Mining Company, which the company describes as a Newmont-Hecla joint venture. About 1 million tons were mined at an average grade of about 0.44 ounces per ton (roughly 15 g/t gold), and the ore was trucked about 120 miles to a Newmont oxide mill. Blossom Gold's approach is different: it is looking at the lower-grade mineralisation around the old workings as a possible bulk-tonnage, open-pit, heap-leach operation.

The current open-pit-constrained inferred mineral resource, with an effective date of 1 November 2025, is 70.755 million tons (short tons) at 0.62 g/t gold and 6.49 g/t silver. That contains about 1.28 million ounces of gold and 13.4 million ounces of silver. All of the resource is in the inferred category.

What the drilling is targeting

The programme covers five zones across an area of about 2 km by 1.6 km: Northwest, Northeast, Southwest, South and East. Drilling focuses on up-dip extensions and on parts of the deposit with little historical drilling. The company is drilling both to expand the resource and to infill it, so that more of the resource could be upgraded to higher-confidence categories. Blossom Gold says the drilling needed for permitting and design is about 80% complete. Highlights reported on 12 August 2026, all from the South zone, include:

  • BG26-030: 115.4 m at 0.553 g/t gold, including 56.2 m at 0.860 g/t
  • BG26-027: 28.0 m at 1.682 g/t gold
  • BG26-024: 25.3 m at 0.864 g/t gold
  • BG26-026: 124.3 m at 0.315 g/t gold, including 34.2 m at 0.664 g/t

The long intervals at grades between about 0.3 and 0.9 g/t fit the heap-leach model the company is pursuing. They are also broadly consistent with the average grade of the existing resource. The first round of expansion and infill results was reported on 30 June 2026.

Metallurgy, underground access and the Kamma claims

Metallurgy is the other main workstream. In May 2026, Blossom Gold finished drilling metallurgical core holes and began sending samples to Kappes, Cassiday & Associates in Reno for heap-leach testing. On 27 August 2026 it reported initial metallurgical results and said it had engaged a metallurgical adviser for the project. The company has also been reopening the old underground workings. In July it announced that the reopening of Portal No. 2 was under way, and on 25 August that rehabilitation of Decline No. 2 had begun. It plans underground as well as surface programmes to support a future feasibility study.

Separately, Blossom Gold is exploring the Kamma claims west of Rosebud. It filed a notice of intent with the US Bureau of Land Management (BLM) in May 2026, received approval in June, and began drilling there on 31 August 2026.

What investors are watching

The company expects to continue resource expansion and infill drilling into the first quarter of 2027, with an updated mineral resource estimate after that. Key questions include how much the updated estimate might add to or upgrade the current 1.28 million ounces, and what leach testing shows about gold recoveries. These will shape any later economic study. How quickly the company spends its C$115 million raise is also relevant.

Risks to consider

Rosebud's resource is entirely inferred and has not yet been shown to be economic. There is no economic study on the open-pit, heap-leach concept, and past underground production at much higher grades does not mean a low-grade open-pit operation would be viable. Heap-leach recoveries can vary a lot between ore types, and the full metallurgical results are still to come. Permitting in Nevada, including on BLM-administered land, can take time. The company's value is also closely tied to the gold price and to its ability to raise more Capital when needed.

Key milestones to monitor

Upcoming milestones include completion of the 24,000-metre programme, further assay results from all five zones, full heap-leach test results from Kappes, Cassiday & Associates, first results from the Kamma claims, progress on the underground rehabilitation, and the updated resource estimate expected after drilling ends in 2027.

Conclusion

Blossom Gold is testing whether a Nevada mine known for high-grade underground ore can support a bulk-tonnage, heap-leach operation. With more than half of its drilling done, broad intercepts at resource-like grades and metallurgical work under way, the next resource update and leach test results will show how well the concept holds up.