From permit to first industrial-scale run

Geomega Resources Inc. (TSXV:GMA) is moving its rare earth magnet recycling technology towards its first industrial-scale demonstration. In June the company received an environmental authorisation from Quebec's environment ministry to operate its demonstration plant in Saint-Hubert, Quebec, and in September it arranged a C$1.35 million secured loan intended partly to fund the plant's development and commissioning. Together, those steps explain why the company is being watched: it is attempting to show that a Canadian process can recover rare earths from magnet waste outside Asia.

Geomega remains a pre-revenue technology and exploration company. Its value depends on whether the demonstration phase produces data good enough to attract magnet manufacturers, licensees or partners, and on whether it can keep financing that work.

Business

Geomega describes itself as a developer of clean technologies for critical minerals. Through its wholly owned subsidiary Innord Inc., it has developed a process to recycle neodymium-iron-boron (NdFeB) permanent magnets, which contain neodymium and praseodymium used in electric vehicle motors and wind turbines. A second technology targets bauxite residue, the waste left from alumina refining, aiming to recover iron, aluminium and critical metals such as scandium, titanium and vanadium while recycling the main reagents. The company also owns the Montviel rare earth carbonatite deposit in Quebec and holds more than 16.8 million shares of Auriginal Mining Corp.

The shares trade on the TSX Venture Exchange as GMA and over the counter in the United States as GOMRF. The company does not pay a dividend.

The demonstration plant and its permit

According to Geomega's release of 3 June 2026, the ministry authorisation allows the Saint-Hubert plant to operate and collect data until 31 December 2028. If results are satisfactory, the company intends to apply for a full commercial environmental permit. At that point all major process equipment had been delivered and installed, piping was expected to finish by the end of July, cabling was complete with connection and testing continuing, and construction was expected to be largely complete by the end of the summer. Magnet feed purchases were being increased to build a stockpile ahead of section-by-section commissioning.

Chief executive Kiril Mugerman has framed the plant as the first time the process will run at industrial scale, with an aim of near-zero solid and liquid waste. Management's stated commercial logic is that monitoring data should help magnet makers evaluate the technology and could lead to licensing. That is a strategy rather than a result: no commercial contract or licence was disclosed in the materials reviewed, and the September loan release referred to the plant as still being developed and commissioned without giving a fresh timetable. Published descriptions of the plant's daily feed capacity also differ between sources, so readers should rely on the company's latest disclosure.

Rio Tinto partnership and the piloting facility

Geomega's bauxite residue work is tied to a Joint Development Agreement with Rio Tinto announced on 8 October 2025. In June the company said a pre-feasibility study under that agreement was well advanced, that Geomega had completed all its deliverables, and that planned payments to it across 2025 and 2026 totalled C$1.5 million. The study is meant to inform Rio Tinto's decision on further engineering, which would precede any decision on building a demonstration plant in Saguenay, Quebec. Any such decision rests with Rio Tinto, and none has been announced.

Separately, Geomega announced an integrated research, development and piloting facility in Saint-Hubert on 17 December 2025. Operating permits have been obtained, and the company expected the multi-level piloting infrastructure to be complete by the end of the summer. Management argues the facility should shorten development cycles and let it test its processes on additional mining and industrial waste streams.

Funding and capital structure

On 16 September 2026 Geomega announced a C$1.35 million secured loan from an arm's-length private lender with which it has an existing commercial relationship. The two-year loan carries interest of 10.5 per cent a year, payable monthly, matures on 14 September 2028 and can be repaid without penalty after six months. Part of the principal is to be repaid as refundable research and development tax credits are received, and the loan is secured over certain movable assets of Geomega and Innord, including those credits. It is not convertible. A 2 per cent fee reduced net proceeds to about C$1.32 million.

The company said the loan accelerates access to tax-credit cash as some government-funded programmes wind down, which signals that working capital is a live consideration. The release did not disclose a total cash balance. A February 2026 release cited 161,725,344 shares in issue and a market value of roughly C$53 million at a C$0.33 closing price; both will have changed since. In the same month Geomega sought to extend 704,028 warrants by a year.

Industry drivers

Demand for NdFeB magnets is linked to electrification, wind power, robotics and defence, while refining and magnet production remain heavily concentrated in China. Western governments have been encouraging alternative supply chains, which supports interest in recycling. Rare earth prices are volatile, however, and recycled oxide must compete on cost and quality with primary supply.

Risks and milestones

Key risks include commissioning delays or underperformance at Saint-Hubert, the challenge of securing reliable magnet feed, dependence on partners and government support, financing and dilution, and the possibility that Rio Tinto does not advance the bauxite residue project. Montviel remains a long-dated asset without disclosed development plans.

Disclosed near-term milestones include completing construction and staged commissioning of the demonstration plant, generating operating data under the permit, completing the Rio Tinto pre-feasibility study and finishing the piloting facility. Updated financial statements and any news on commercial licensing would help clarify the company's position.