Silver Mountain Resources Inc. (TSX:AGMR) has spent 2026 rebuilding the underground workings, stockpiles and processing plant needed to bring Peru's historic Reliquias silver mine back into production. On 21 September 2026 it reached the first major milestone: the company announced that it had produced its first bulk and zinc concentrates in mid-September. Its focus now moves from preparing for the restart to ramping up production.

The milestone came about seven months after Silver Mountain moved from the TSX Venture Exchange to the Toronto Stock Exchange on 26 February 2026. Its common shares kept the AGMR symbol, and its listed warrants continued to trade as AGMR.WT.B. The shares also trade on the Lima Stock Exchange (BVL: AGMR) and on the OTCQB in the United States under AGMRF.

Company overview

Silver Mountain is a Toronto-headquartered company focused on silver in Peru. Its main asset is the 100%-owned Reliquias mine, an underground silver-polymetallic deposit in the Castrovirreyna district of Huancavelica in central Peru. Through its Subsidiary Sociedad Minera Reliquias, the company holds more than 60,000 hectares in the district, including the nearby Caudalosa mine and the concentrator plant used to process Reliquias ore. Alvaro Espinoza is chief executive.

How the restart was prepared

The company's disclosures in 2026 show steady progress through each part of the restart:

  • January 2026: about 1,500 metres of underground development completed, about 2,500 tonnes stockpiled and the tailings storage Facility rehabilitated, with a treasury above US$32 million
  • April 2026: more than 3,000 metres of development, about 12,000 tonnes stockpiled, all major plant equipment delivered and camp, power and water-treatment infrastructure operational; the company said it was fully funded, with more than US$30 million
  • May 2026: rehabilitation of the processing plant reported as 75% complete
  • July 2026: plant rehabilitation about 95% complete; commissioning began in early July using low-grade ore
  • September 2026: first bulk and zinc concentrates produced in mid-September

By July, the crushing circuit was running, and the grinding and flotation circuits, including a refurbished 9-by-11-foot ball mill, had completed no-load tests. The company attributes much of the restart's relatively low Capital cost to the existing permitted infrastructure, including the tailings facility, power connection and water-treatment plant.

First concentrate and the ramp-up plan

According to the 21 September announcement, initial plant feed is coming from about 45,000 tonnes of mineralised material stockpiled during underground development. Silver Mountain expects throughput and feed grades to rise gradually during ramp-up and is targeting 800 tonnes per day in the second half of 2027. It expects concentrate shipments to begin in October 2026. Espinoza described the milestone as the company's transformation from developer to producer.

Project economics: the 2024 PEA

The restart is based on a preliminary economic assessment (PEA) with an effective date of 15 May 2024. It was later amended and restated in a NI 43-101 technical report dated 28 October 2024. Key figures, which assumed a silver price of US$24 per ounce, include:

  • Pre-tax NPV at a 5% discount rate of C$107 million, with a pre-tax IRR of 57%
  • After-tax NPV (5%) of C$85 million, with an after-tax IRR of 51%
  • Initial capital of US$24.8 million and a payback period of 1.8 years
  • Average production of 2.2 million ounces of silver equivalent a year over a nine-year mine life
  • All-in sustaining cost of US$17 per ounce of silver equivalent

The PEA mine plan envisaged Mining about 2.4 million tonnes at average head grades of 3.71 ounces per tonne silver, 0.32 g/t gold, 2.45% zinc, 1.62% lead and 0.26% copper, producing a bulk concentrate and a zinc concentrate. The project is about 250 km by road from the Port of Callao.

Silver Mountain expects to publish an updated mineral resource estimate and an updated PEA in the fourth quarter of 2026. On its website at the time of writing, the company quoted silver at about US$67 per ounce, well above the price assumed in the PEA.

Funding, permits and community agreements

The company raised money through bought-deal financings in 2025, including an upsized offering of about C$30 million that closed in November 2025. It has also cited a range of approvals and agreements: approval from Peru's Ministry of Energy and Mines in December 2024 to restart Reliquias and the Caudalosa plant, an environmental permit extension to 2034, and a 20-year land-use agreement with the Salcca Santa Ana community signed in July 2025.

District growth beyond Reliquias

Alongside the restart, Silver Mountain began a 7,000-metre underground infill drilling programme at Reliquias in February 2026 to upgrade resources and support mine planning. In March 2026 it launched a 14,000-metre first-phase programme at Caudalosa, which the company says hosts a historical resource. Historical estimates are not current mineral resources and should not be relied on as such.

Risks to consider

The company itself stresses that the decision to restart Reliquias was not based on a feasibility study of mineral reserves. The PEA includes inferred resources, which make up about 57% of the resources it uses, and Silver Mountain warns that production decisions without a feasibility study carry greater technical and economic uncertainty. Ramp-ups often take longer than planned, and actual grades, recoveries and costs may differ from estimates. Other risks include silver and base-metal price swings, Peru's political and regulatory environment, community relations, and the possible need for more financing.

Key milestones to monitor

Near-term markers include the first concentrate shipments, expected in October 2026; throughput and grade reporting as the plant ramps up towards 800 tonnes per day; the updated resource estimate and PEA expected in the fourth quarter of 2026; and drill results from the Reliquias infill programme and the Caudalosa campaign. Any quarterly financial statements that show early sales Revenue will also be closely watched.

Conclusion

Silver Mountain's preparations have now led to first concentrate at Reliquias, moving the TSX-listed company from developer to early-stage producer. The next test is operational: showing that the plant can ramp up steadily, that grades remain in line with expectations and that shipments turn into cash flow. The updated technical studies due later in 2026 should give investors a clearer view of the mine's longer-term potential.