Silver Tiger Metals Inc. (TSX:SLVR) moved from technical studies to construction at its El Tigre silver-gold project in Sonora, Mexico, in a short sequence of steps. It secured federal environmental approvals in November 2025 and published an updated pre-feasibility study (PFS) in January 2026. It then raised Equity in February, and in March 2026 its board approved a construction decision and signed an engineering, procurement and construction management (EPCM) contract. Management is now targeting commissioning and first pour in December 2027.
Along the way, Silver Tiger graduated from the TSX Venture Exchange to the Toronto Stock Exchange, where its shares began trading under the unchanged symbol SLVR on 21 May 2026. The company also trades on the OTCQX as SLVTF. Its most recent update, on 21 September 2026, brought both a larger Capital cost estimate and a new C$87 million bought deal financing.
Company overview
Halifax-based Silver Tiger owns 100% of the El Tigre project, which covers more than 37,000 hectares in Sonora. The district hosts the historic El Tigre mine. The company's near-term focus is the Stockwork Zone, a near-surface deposit planned as an open-pit, heap leach operation producing silver and gold. A separate underground project, aimed at higher-grade veins, sits behind it as a potential second phase.
From permits to a construction decision
The first milestone came on 7 November 2025, when Silver Tiger announced it had received all required approvals and permits from SEMARNAT, Mexico's federal environmental authority, to build the El Tigre Stockwork Zone project. Permitting timelines in Mexico have become a closely watched issue for developers, so securing these approvals early removed a major gating item.
On 20 January 2026 the company released two studies, based on silver at US$38/oz and gold at US$3,200/oz:
- Updated Stockwork Zone PFS: after-tax NPV of US$456 million, after-tax IRR of 65.7%, payback of 1.4 years, a 10-year mine life and initial capital of US$86.8 million
- Stockwork Zone PFS recovered metal: about 43 Moz silver equivalent, including roughly 9 Moz silver and 408,000 oz gold
- Underground preliminary economic assessment (PEA): after-tax NPV of US$304 million, after-tax IRR of 42.8% and initial capital of US$83.5 million over a production period of about 17 years
A PEA is preliminary in nature and includes inferred resources that are too speculative geologically to be classified as reserves, so the underground results carry more uncertainty than the PFS.
Funding and the EPCM contract
Silver Tiger launched a bought deal in late January 2026 that was upsized and closed on 18 February 2026 for gross proceeds of about C$57.5 million. On 18 March 2026 the board approved the construction decision for the Stockwork Zone. The company signed an EPCM contract with Kappes, Cassiday & Associates (KCA) and its Mexican affiliate, Kappes, Cassiday del Norte (KCN).At the time, the company reported cash of more than US$86 million and said Debt Financing term sheets were advanced. It has also hired its own mine construction executive team to work alongside the contractors.
Construction progress at El Tigre
The company's 14 September 2026 update said construction remained on schedule for commissioning and first pour in December 2027. It reported the following progress:
- More than 250 people on site, with 219,000 hours worked since construction began
- Detailed engineering 65% complete
- Mine operations camp 50% complete
- Upgrades to the 46 km access road from Colonia Morelos 85% complete
- Earthworks for the heap leach pad, ponds and plant platforms 30% complete
- Long-lead items procured, including the crushing plant, conveying and stacking system, and Merrill-Crowe plant and refinery
The same release said Silver Tiger would be added to the VanEck Junior Gold Miners ETF (GDXJ) at the September 2026 quarterly rebalance. Management said the inclusion could improve trading liquidity.
Higher capital costs and a new C$87 million raise
On 21 September 2026, Silver Tiger said the estimated construction capital for the Stockwork Zone had risen to about US$124 million. That is roughly US$37 million above the initial estimate in its 2026 technical report, and comprises about US$108 million under the EPCM and US$16 million managed directly by the company. The company gave three reasons. Industry cost escalation added an estimated 10%. Additional geotechnical drilling added about US$25 million to earthworks, as the Volume of material needing blasting nearly doubled. Binding Supply contracts for major equipment also came in above the study's assumptions. The company reminded readers to consider the impact of the higher estimate on the PFS economics.
As of 10 September 2026, Silver Tiger had committed about US$81 million (roughly 66% of the updated budget) and spent about US$17 million. To cover the gap, it agreed a bought deal with a syndicate led by Stifel Canada. The deal comprises 87 million units at C$1.00, each with one share and half a Warrant exercisable at C$1.35 for 24 months, for gross proceeds of C$87 million, or about C$100 million if the over-allotment option is fully exercised. Closing is expected on or about 13 October 2026. The company estimated its current cash at about C$90 million, and pro forma cash at about C$173 million against an estimated C$150 million of remaining capital expenditure.
Risks to consider
The capital cost increase shows how quickly budgets can change during construction, and further overruns or delays remain possible. The new financing is not closed and will dilute existing shareholders, and the warrants could add more shares. Project returns are sensitive to silver and gold prices, which have been volatile, and the study Economics predate the cost update. Mexico carries jurisdictional risks, including changes to Mining policy, permitting and security. Heap leach recoveries also have to be demonstrated in commercial operation.
Key milestones to monitor
Investors are likely to watch the closing of the C$87 million offering, progress on earthworks and detailed engineering, and whether the December 2027 first-pour target holds. They may also look for any update on the debt financing discussed earlier in the year, and for how the underground PEA advances as a potential second phase.
Conclusion
Silver Tiger's path at El Tigre, from SEMARNAT approval through the PFS and financing to the EPCM award, has turned a study-stage project into an active build, with the company now listed on the TSX. The higher capital estimate is a reminder that execution risk is part of the story. The company says the proposed raise, if completed, would leave it funded for the estimated remaining capital expenditure.