Key Highlights

  • Silver X Mining Corp (TSXV: AGX) processed a record 62,252 tonnes of ore at Nueva Recuperada in Q2 2026, up 39% quarter-on-quarter.
  • Net Operating Revenue reached $17.3 million in Q2 2026, up 29% quarter-on-quarter and 221% higher year-on-year.
  • Silver-equivalent output rose 57% quarter-on-quarter to 283,029 ounces, with daily throughput peaking at 751 tonnes, close to the plant's roughly 750 tpd design rate.
  • All-in sustaining costs fell 13% quarter-on-quarter to $46.10 per AgEq ounce.
  • A March 2026 C$69.0 million convertible Debenture left the company with $49.7 million in cash at quarter-end.
  • Management targets a 1,000 tonne-per-day processing run rate in the third quarter of 2026, with a longer-term ambition of 1,500 tpd.

A Quarter of Records for the Peruvian Silver Hopeful

Silver X Mining Corp (TSXV: AGX) told the market on 9 July 2026 that its Nueva Recuperada operation in Peru's Huancavelica region had delivered record quarterly production for the three months to 30 June 2026, processing 62,252 tonnes of ore — a company record and up 39% on the first quarter. It followed up on 6 August 2026 with record second-quarter financial results, reporting net operating revenue of $17.3 million, up 29% quarter-on-quarter and 221% higher than a year earlier.

Together, the two releases describe a Business moving from a modest, single-mine polymetallic producer towards one running close to permitted plant capacity, with output, revenue and cash generation all rising in tandem.

Why the Milestone Matters

Junior silver producers are frequently long on resource potential and short on delivery. Silver X's latest quarter matters because it shows the Nueva Recuperada plant actually running near nominal capacity rather than merely being guided towards it: daily throughput averaged 684 tonnes and peaked at 751 tonnes per day in April, close to the plant's roughly 750 tpd design rate.

Chief executive José M. García said the quarter demonstrated the Operating Leverage of Nueva Recuperada, citing the throughput gain and a sharp rise in gold output as evidence the mine and plant can absorb more tonnes without a proportional cost blow-out.

Inside Nueva Recuperada

Nueva Recuperada is Silver X's flagship silver-gold-lead-zinc polymetallic complex in central Peru, comprising several underground mining units feeding a central concentrator. The district-scale land package underpins both current production and exploration targets including the Tangana and Red Silver zones and the more recently consolidated Pampas project.

Underground development advanced to 3,159 metres in the second quarter, up from 2,440 metres in the first, laying groundwork for higher mining rates ahead. In June 2026, Silver X added the Lily 19 (Ccasahuasi) claims from Barrick Gold for a modest $30,000 cash consideration.

Throughput, Grades and Output

The company reported 283,029 silver-equivalent ounces produced in the second quarter, up 57% from the first quarter. Silver output was 145,885 ounces and gold output 1,404 ounces, both up sharply on the first quarter, while gold head grades averaged 1.10 g/t.

Year-on-year, growth is starker still: processed tonnage was up 78% and silver ounces up around 75% versus the second quarter of 2025, while gold ounces more than tripled.

Revenue, Costs and the Balance Sheet

The June quarter's $17.3 million of revenue produced Operating Income of $7.5 million and adjusted EBITDA of $6.9 million, both records. Net Income was $3.1 million, lower than the first quarter's $4.6 million despite higher revenue — the company attributes this to finance costs, taxes and foreign-exchange effects rather than weaker operations. Unit costs improved, with all-in sustaining costs falling 13% quarter-on-quarter to $46.10 per AgEq ounce.

Silver X ended the quarter with $49.7 million in cash, Working Capital of $35.1 million, and shareholders' Equity of $46.7 million. The balance sheet was reshaped in March 2026 by a C$69.0 million convertible debenture carrying a 10% coupon, maturing in 2031, giving the company a cash cushion to fund growth plans without immediate reliance on further equity dilution.

Expansion Plans and Key Risks

Management's near-term target is a 1,000 tpd processing run rate during the third quarter of 2026, up from roughly 700 tpd in the second, with a longer-term ambition of 1,500 tpd pending an Environmental and Social Impact Assessment update and Tangana mining unit permits expected during 2027. The company has also expanded its Red Silver drill programme five-fold to 6,650 metres after channel sampling returned a reported 735 g/t silver over 65 metres.

Silver X remains reliant on a single mining district for essentially all of its Cash Flow , so any disruption at Nueva Recuperada — from ground conditions, equipment availability, labour relations or permitting issues — would have an outsized impact. The business also remains exposed to swings in silver, gold, lead and zinc prices, foreign-exchange movements, and obligations created by the new convertible debenture.

Conclusion

The results have landed against a strong silver price backdrop, with spot silver trading above $58 an ounce in early August 2026. The next checkpoints are confirmation of the targeted 1,000 tpd run rate in the third quarter, progress on the ESIA for the 1,500 tpd expansion, permitting news on the Tangana mining unit, and updates from the expanded Red Silver drilling programme — all of which will show whether the June quarter's momentum can be sustained rather than proving a single strong print.