Key Highlights

  • Average LME copper rose 39.8% year on year to $6.04 per pound, while mined copper output fell 3.5%.
  • Net income attributable to the company was $1,670.0 million, up 71.6%, or $2.01 per diluted share.
  • Mined copper production was 230,662 tonnes in the quarter, against 238,980 tonnes a year earlier.
  • On a GAAP basis, Operating Income was $2,623.2 million, with cost of sales, excluding depreciation, of $1,389.5 million.

Southern Copper Corporation (NYSE:SCCO) (NYSE: SCCO) reported second-quarter 2026 results on July 21, 2026 showing much stronger sales and profit, even though it mined less copper. Price explains it. Average LME copper rose 39.8% year on year to $6.04 per pound, while mined copper output fell 3.5%.

Price, not volume, drove the quarter

Net sales reached $4,289.0 million, up 40.6%. Net Income attributable to the company was $1,670.0 million, up 71.6%, or $2.01 per diluted share. Chairman German Larrea said the company registered "record-breaking results in sales, adjusted EBITDA, and net income". All figures are in US dollars and relate to calendar quarters.

What Southern Copper does

Southern Copper mines, smelts and refines copper in Mexico and Peru, and produces molybdenum, silver and zinc as by-products. Its common stock trades on the New York Stock Exchange and on the Lima Stock Exchange under the same ticker. The company reported 834.3 million shares outstanding at June 30, 2026.

Operating evidence

Mined copper production was 230,662 tonnes in the quarter, against 238,980 tonnes a year earlier. Mexican operations rose 3.2% from the first quarter, but Peruvian mines fell 12.0%. The company attributed the year-to-date decline mainly to lower ore grades in Peru. First-half mined copper totaled 461,206 tonnes, down 3.8%.

By-products also softened on volume. Mined molybdenum fell 11.0% to 7,046 tonnes, and mined zinc fell 14.5% to 39,257 tonnes, mainly because of lower output at the Buenavista zinc concentrator. Mined silver slipped 3.8% to 5,759 thousand ounces. Prices offset much of this: average silver rose 118.6% and molybdenum 43.1%.

GAAP profit and non-GAAP measures

On a GAAP basis, operating income was $2,623.2 million, with cost of sales, excluding depreciation, of $1,389.5 million. Net income Margin was 38.9%, compared with 31.9% a year earlier.

Adjusted EBITDA, a non-GAAP measure, was $2,856.0 million, a margin of 66.6%. Operating cash cost per pound of copper, also non-GAAP, was 228.8 cents before by-product credits, up from 211.2 cents. Net of by-product credits it fell to 4.6 cents from 63.1 cents, reflecting stronger by-product prices rather than lower spending.

First-half Operating Cash Flow was $3,683.0 million, up 116.9%, and capital investments were $864.7 million. At June 30, cash and equivalents stood at $5,665.0 million, plus $1,664.9 million of short-term investments, against long-term Debt of $7,994.4 million.

Growth projects and financing

The company describes a capital program exceeding $20.5 billion this decade. Tía María in Arequipa, Peru, designed for 120,000 tonnes a year of copper cathode, was 42% complete at June 30, with start-up expected in the second half of 2027. In June the company priced $1.25 billion of 5.350% notes due 2036.

In Mexico, El Pilar in Sonora has environmental permits, with early site work scheduled from September 2026, construction from the first quarter of 2027 and start-up targeted for the second half of 2029. Los Chancas and Michiquillay in Peru carry expected starts of 2031 and 2032.

Dividend

On July 16, 2026 the board declared a cash Dividend of $1.10 per share plus a Stock Dividend of 0.0120 shares per share, payable on August 27 to holders of record on August 11.

Metal Price Swings and Unit Costs Carry the Risks

The quarter shows how sensitive Earnings are to metal prices. Unit costs before by-product credits rose, and volumes fell, so a Reversal in copper or silver prices would hit margins quickly. Peruvian grades, community and permitting issues, illegal Mining around Los Chancas and Mexican power infrastructure for El Arco are further risks the company flags.

The next dated milestones are El Pilar site preparation this month and Tía María construction progress. The release did not include full-year production guidance, so future output assumptions deserve caution.