Key Highlights
- STLLR Gold Inc (TSX: STLR) reported 13.00 g/t gold over 22.75 metres at the Jonpol deposit, part of the Tower Gold Project near Timmins, Ontario.
- A capped, resource-relevant grade of 7.37 g/t gold over 16.66 metres true thickness was also disclosed alongside the uncapped headline figure.
- Tower carries a combined resource of roughly 11 million ounces, split between 4.0 million Indicated and 7.0 million Inferred ounces.
- A 2025 PEA modelled a 19-year mine life producing an average 273,000 ounces annually, with an after-tax NPV of roughly C$1.36 billion at US$2,500/oz gold.
- The 2026 drill programme aims to extend Jonpol's mapped strike from roughly 400 metres to around 1,200 metres.
- Tower benefits from established Timmins-camp infrastructure, including paved highways and grid power, factored into the PEA's roughly C$1.87 billion initial Capital estimate.
A Standout Intercept at Jonpol
STLLR Gold Inc (TSX: STLR) said on 18 June 2026 that diamond drill hole MGA26-268 had returned 13.00 g/t gold (uncapped) over 22.75 metres — including a higher-grade core of 29.09 g/t gold over 9.91 metres — at the Jonpol deposit within its wholly owned Tower Gold Project near Timmins, Ontario. A companion hole intersected 3.01 g/t gold over 22.93 metres, including 11.95 g/t gold over 4.80 metres.
Notably, the company also disclosed a capped, outlier-adjusted grade for the headline intercept of 7.37 g/t gold over a true thickness of 16.66 metres, reflecting standard practice of moderating very high assay values before they feed resource models. The uncapped figure drove the headlines, but the capped number is the more conservative, resource-relevant one.
Timing Meets a Historic Gold Camp
The hit lands as gold does much of the talking. Bullion has traded at successive record highs through 2026, changing hands at roughly US$4,350 an ounce in early August, supported by soft US labour data, Federal Reserve rate-cut expectations, Inflation concerns and continued central-bank accumulation.
Jonpol sits within the broader Timmins Gold Camp, one of North America's most prolific gold-producing districts, alongside operations run by majors including Newmont and Agnico Eagle. High-grade, near-surface intercepts in an established camp tend to draw disproportionate attention because they speak to both grade quality and the potential to shorten the path to production.
Inside the Tower Gold Project and Jonpol Deposit
Tower is STLLR's flagship asset, an amalgamation of historic gold properties — including the former Garrison project — consolidated under one 100%-owned land package roughly 100 kilometres east of Timmins along Highway 101. Jonpol has become the focus of 2026 exploration because of its high-grade, near-surface mineralisation, which management has flagged as offering some of the best per-metre metal content intersected at Tower to date.
The 2026 programme at Jonpol has two goals: extending the deposit's known strike length, and infilling to de-risk the geological model ahead of a future resource update. As of the June disclosure, the programme had completed 8,536 metres of drilling, targeting an extension of Jonpol's mapped strike from roughly 400 metres to around 1,200 metres.
An 11-Million-Ounce Resource Base
The Jonpol intercepts sit against a substantial project-wide resource. STLLR's most recent Mineral Resource Estimate, published alongside a Preliminary Economic Assessment in May 2025, outlined 4.0 million ounces Indicated and 7.0 million ounces Inferred across Tower — a combined 11 million ounces. Jonpol itself was a comparatively small contributor at the time, underscoring why the 2026 drilling is being watched closely: successful strike extension could materially grow Jonpol's share of the overall resource.
The 2025 PEA modelled a 19-year conceptual mine life producing an average 273,000 ounces of gold annually — peaking above 300,000 ounces in several years — for total life-of-mine output of about 5.2 million ounces. At a base-case US$2,500/oz gold price, the study showed an after-tax net present value of roughly C$1.36 billion and a 13.4% after-tax internal rate of return, rising to C$3.30 billion NPV and 24% IRR under a spot-price scenario of US$3,200/oz — a figure gold has since surpassed.
Exploration Upside and Regional Infrastructure
The exploration case for Jonpol rests on the gap between its currently modelled 400-metre strike and geological indications that mineralisation continues well beyond that envelope. Management's target of tripling the tested strike length to around 1,200 metres, if borne out by assays, would represent a meaningful re-rating of the deposit's contribution to Tower's inventory — though this remains an exploration target rather than a defined resource.
One of Tower's recurring selling points is its location, benefiting from proximity to established regional infrastructure — paved highways, grid power distribution and local Supply chains built up over more than a century of Mining activity around Timmins — rather than the greenfield infrastructure spend typical of remote projects. That positioning feeds into the PEA's capital-cost assumptions, which modelled initial capex of roughly C$1.87 billion.
Funding, Governance and Key Risks
STLLR has funded recent exploration through a series of Equity raises, including bought-deal and concurrent private Placement financings. Alongside the 4 August 2026 drill update, the company disclosed a routine board change, with a director resigning effective 1 August 2026 to focus on other commitments.
As with any pre-production exploration company, STLLR's shares carry meaningful risk. Tower remains at the PEA stage — a conceptual-level study with lower accuracy than a pre-feasibility or feasibility study — and its Economics are highly sensitive to gold-price assumptions. Individual high-grade intercepts do not change the resource until incorporated into an updated, independently reviewed estimate, and STLLR will need substantial additional capital to advance Tower, alongside permitting and further engineering before any construction decision.
Conclusion
Those tracking the story should watch for three things: outstanding 2026 assays from Jonpol, particularly step-out holes testing the western strike extension; any formal timeline STLLR provides for an updated Mineral Resource Estimate; and ongoing financing activity, which will indicate how the company intends to fund continued exploration and the next stage of technical studies at Tower.






Please wait processing your request...