Back on the ground at Tenoriba

Mammoth Resources Corp. (TSXV:MTH) is trying to turn a long-studied Mexican gold-silver property into its first mineral resource. In late August 2026 the company said field crews had started work at its wholly owned Tenoriba project in Chihuahua State, reviewing historical drill core, checking access and drill pad locations for a permitted 60-hole Phase 1 programme, and collecting material for leach testing. A further update on field work, metallurgical testing and exploration followed on 22 September 2026. The central question is whether this very small company can fund and complete the drilling needed to define a maiden resource.

Mammoth is a Toronto-based precious metals explorer focused on Mexico and other mining-friendly jurisdictions in the Americas. Its sole disclosed asset is Tenoriba, a 5,333-hectare property in the Sierra Madre precious metal belt of south-western Chihuahua, subject to a 2% net smelter Royalty that can be bought back for US$1.5 million within two years of commercial production. The company also has a strategic alliance with RM Mineria S de RL de CV, a Mexican group, under which it is pursuing acquisitions of near-term producing mines, although no specific transaction has been announced.

Listing details and index position

The company's shares trade on the TSX Venture Exchange under the symbol MTH. The shares showed a last close of C$0.03 on 26 August 2026, with 106,556,933 shares in issue and a Market Capitalisation of roughly C$3.2 million.

No evidence was found that Mammoth belongs to the S&P/TSX Venture Composite Index or any other S&P/TSX benchmark. A venture listing is not the same as index membership.

Exploration target and drilling plan

Mammoth drilled Tenoriba in 2021 and 2022, and earlier work covers 55 diamond holes across about four kilometres of strike in three main areas: Carneritos, Masuparia and Moreno. A 2023 drill hole spacing study by P&E Mining Consultants recommended 80-metre spacing at Carneritos and Moreno and 40-metre spacing at Masuparia to support an Inferred resource. Cyanide bottle-roll tests on Carneritos samples indicated rapid gold dissolution, which the company says supports potential low-cost heap leaching of near-surface oxide and transition material.

In May 2024 Mammoth published an Exploration Target of about 1.7 to 1.9 million gold-equivalent ounces, using a silver-to-gold ratio of 75 to 1. Readers should treat this carefully: an Exploration Target is conceptual, is not a mineral resource, and the company itself says further drilling only has the potential to define resources. In April 2026 Mammoth said updated contractor quotes put all-in drilling costs at about US$304 a metre. Phase 1 is planned as 60 shallow holes, each about 50 metres deep, totalling 3,000 metres at Carneritos for roughly US$910,000, or about C$1.25 million. A second phase of 102 holes across all three areas would bring the combined programme to around US$2.3 million.

In February 2026 the company also identified six potential draw points at Carneritos, where surface sampling averaged roughly 1 to 3.9 g/t gold equivalent, for a possible pilot leach test and small-scale extraction. The August field programme includes collecting up to 200 kilograms of material from these areas for column leach tests.

Finances and funding needs

Mammoth reports in Canadian dollars and has a 31 January financial year end. Its most recent filing is an interim report for the three and six months ended 31 July 2026, released on 26 September 2026. Figures for the year to 31 January 2025 show a net loss of about C$453,000, operating cash outflow of about C$77,000 and negative shareholders' Equity of about C$788,000, indicating that liabilities exceeded Assets at that date.

Funding has come from small private placements. In mid-2025 Mammoth raised C$980,000 by issuing 39,222,300 units at C$0.025, each with half a warrant, and closed the final Tranche on 18 August 2025. The financing supported the RM Mineria alliance, with Jose Antonio Berlanga Lopez acquiring a 19.2% interest. No new financing to pay for the Phase 1 drilling has yet been announced, and the planned budget of about C$1.25 million is large relative to the company's market value.

Mammoth does not pay a dividend, and both trailing and indicated yields are nil, which is consistent with an exploration company that has no revenue.

Gold and silver backdrop

Precious metal prices provide a supportive setting. In April 2026 Mammoth's chief executive, Thomas Atkins, pointed to gold trading above US$5,000 an ounce as a reason to pursue low-cost resource definition. Strong prices tend to improve the Economics of low-grade heap-leach deposits and can make investors more willing to fund explorers. Even so, small Mexican explorers face permitting scrutiny, community access negotiations and security considerations, and capital has tended to favour larger companies with defined resources.

Principal risks

Financing is the main risk. Mammoth's Market Value is a fraction of its drilling budget, so any raise is likely to be highly dilutive, and failure to raise funds would delay the programme. The company has also noted that it was still confirming the standing of its drill permit and re-engaging the local community on surface access, so practical approvals remain a dependency.

Geological risk is significant. Grades at Tenoriba are modest, often below one gram per tonne gold equivalent over long intervals, and conversion of an Exploration Target into resources is far from assured. Metallurgical tests could disappoint, and heap-leach economics are sensitive to recoveries, reagent use and metal prices. Finally, the planned Acquisition strategy with RM Mineria is undefined, and any deal could change the company's risk profile.

Milestones to monitor

The company has flagged several next steps: confirmation of drill access and permits, results from column leach tests on Carneritos material, financing for the 60-hole Phase 1 programme, and eventually a maiden Inferred resource estimate. Annual results for the year ending 31 January 2027 would normally be filed by mid-2027. Until then, the evidence rests mainly on historical drilling, conceptual targets and early field work.