A Mine Is a Wasting Asset
Mine life is the number of years a deposit can keep producing based on its mineral reserves. Reserves are the portion of a deposit that has been studied in enough detail to show it can be mined profitably. A factory can run for decades. A mine digs up its own inventory, and every ounce sold is one that cannot be sold again.
Mine life matters to investors for three reasons. First, a company's valuation largely depends on how many years of Cash Flow lie ahead. Second, a short mine life forces a company to spend on exploration, construction or acquisitions just to stand still. Third, when a mine closes, production falls sharply and the company still has rehabilitation costs to pay.
B2Gold and DPM Metals, known until 2025 as Dundee Precious Metals, both face this problem now. B2Gold is replacing ounces by building new mines across four countries. DPM is extending an ageing flagship, closing a smaller mine and preparing its next development in Serbia.
B2Gold (TSX:BTO): Building Its Way to Longer Life
B2Gold (TSX:BTO) produced 203,648 ounces of gold in Q2 2026 from four mines: Fekola in Mali, Masbate in the Philippines, Otjikoto in Namibia and Goose in Nunavut. It narrowed its 2026 guidance to 820,000–920,000 ounces.
Much of B2Gold's mine-life story depends on Goose, which reached commercial production in October 2025. The company's August 2026 presentation lists Probable Reserves of 2.38 million ounces at a high grade of 6.79 grams of gold per tonne. Its life-of-mine plan sets out about nine years of production, including a five-year steady state averaging roughly 311,000 ounces a year. There is further upside in the wider Back River district, including inferred resources at Nuvuyak and the George project. Inferred resources are the least certain category of mineral estimate.
The other key development is at Fekola. On 7 August 2026, Mali issued the long-delayed exploitation permit for Menankoto, known as Fekola Regional. Management expects that project to produce more than 150,000 ounces a year from 2028 through the mid-2030s. That would help lift the Fekola complex to about 500,000 ounces annually. At Otjikoto, the planned Antelope underground deposit could begin production as early as 2028, under a preliminary study that envisages five years at about 65,000 ounces a year. Further out, the Gramalote project in Colombia has a feasibility study outlining a 13-year life, with pre-production Capital of about US$740 million.
The trade-off is cost. B2Gold's 2026 AISC guidance is US$2,370–2,550 an ounce. AISC, or all-in sustaining cost, is the full cost of producing an ounce and maintaining operations. B2Gold's figure is high partly because of the heavy stripping and development work needed to extend its mines. Goose was also set back by a crusher fire in April, producing just 12,890 ounces in the quarter, and steady-state throughput is not expected until 2027. Operating Cash Flow was negative US$78.8 million in Q2, as cash taxes and a priority Dividend to the Malian state combined with gold prepay contracts that reduced its realised price to US$3,767 an ounce. Management said those contracts end this year. Despite the negative cash flow, B2Gold bought back about 35 million shares for US$172 million year-to-date and still pays a quarterly dividend of US$0.02.
DPM Metals: Extending a Flagship, Closing a Mine
DPM's (TSX:DPM) mine-life challenge played out in Bulgaria this year. On 15 July 2026, the Ada Tepe open-pit gold mine ceased operations and moved into rehabilitation after reaching the end of its reserves. That leaves Chelopech, a gold-copper underground mine, as DPM's anchor asset. In February 2026 the company extended Chelopech's life to ten years with an updated reserve estimate and mine plan. In June it announced the Brevene South porphyry discovery near the mine. A porphyry is a large, typically lower-grade copper-gold deposit that can support long operating lives. DPM also expects an initial resource estimate for Chelopech's Wedge Zone by the end of 2026.
The company's other growth sources are Vareš, a silver-zinc-lead mine in Bosnia and Herzegovina acquired with Adriatic Metals and on track to reach 850,000 tonnes a year by the end of 2026, and Čoka Rakita in Serbia. A November 2025 feasibility study valued Čoka Rakita at US$782 million on an NPV5% basis, meaning the present value of future cash flows discounted at 5% a year, with an internal rate of return of 36%. Construction is targeted for early 2027, pending approval of a special spatial plan expected in the second half of 2026.
At present, DPM (TSX:DPM) is generating plenty of cash. In Q2 2026 it produced 102,690 gold-equivalent ounces, a measure that converts its copper, silver and other metals into gold-ounce terms. Its AISC was US$1,214 an ounce, and free cash flow reached a record US$227.3 million. It held US$761.2 million in cash with no debt, plus an undrawn US$400 million Credit facility.
The Two Approaches Side by Side
|
Metric |
B2Gold |
DPM Metals |
|---|---|---|
|
Q2 2026 production |
203,648 oz gold |
102,690 oz gold equivalent |
|
2026 production guidance |
820,000–920,000 oz |
305,000–365,000 GEO |
|
2026 AISC guidance |
US$2,370–2,550/oz |
US$1,300–1,450/oz |
|
Cash at 30 June 2026 |
US$287M |
US$761.2M (no debt) |
|
Recent mine-life milestone |
Fekola Regional permit (Aug 2026) |
Chelopech extended to ten years (Feb 2026) |
|
Mine closure in 2026 |
None |
Ada Tepe (July 2026) |
|
Next major project |
Gramalote (Colombia) |
Čoka Rakita (Serbia) |
Different Risks Behind Each Approach
Longer mine life does not help investors if the ounces cannot be mined safely and profitably. B2Gold's growth is concentrated in Mali, where the state holds 20% of Fekola and 35% of Fekola Regional, and where the government has pushed for a larger share of Mining revenue. B2Gold also needs Goose, a remote Arctic operation, to reach steady output.
DPM's risks are timing and permitting. Ada Tepe's ounces have already been lost, and Čoka Rakita will not add production until its construction is complete. The company also depends on Chelopech continuing to perform. Vareš is still ramping up and remains exposed to base-metal prices.
The Bottom Line
Mine life measures how long current cash flows can continue. B2Gold is extending its production base by building and permitting new mines in Nunavut, Mali, Namibia and Colombia, which means higher costs and uneven cash flow in 2026. DPM is doing something different: it has closed one mine, extended its flagship and is funding a Serbian project from a debt-free Balance Sheet with lower costs. Both companies need to add ounces. The difference is how much each is spending to do so, and how much execution and jurisdictional risk comes with the new ounces.