Minnova Corp. (TSXV: MCI) (OTC Pink: AGRDF) has made publicly available its National Instrument 43-101 Technical Report supporting the Preliminary Economic Assessment (PEA) for its 100%-owned PL Gold Mine in Manitoba. The release also corrects a previously disclosed underground mining start date and outlines significant resource expansion opportunities at the project. Additionally, the company announced a proposed debt settlement of $225,000 through the issuance of common shares, adding a capital structure element for investors to monitor.
Key Points
- Minnova Corp. (TSXV: MCI) (OTC Pink: AGRDF) is a near-term gold producer focused on the PL Gold Mine in Manitoba's Flin Flon Greenstone Belt.
- The NI 43-101 Technical Report on the PL Gold Mine PEA, prepared by independent consultants A and B Global Mining (Pty) Ltd, has been made publicly available on the company's website.
- PEA base-case highlights include an after-tax NPV of US$180.6 million, after-tax IRR of 111%, and a payback of 0.7 years at US$3,000/oz gold, with pre-production capital of US$53.4 million.
- Investors may be watching for TSX Venture Exchange approval of the proposed debt settlement and progress toward a Pre-Feasibility Study.
Underground Start Date Correction and PEA Economic Highlights Unchanged
The company's October 14, 2026 PEA news release incorrectly stated that underground mining would begin in mid-2028. The technical report and PEA financial model confirm that underground development starts in January 2029, with mineralized material production commencing in March 2029 and no underground tonnes mined in 2028. The correct underground mining period is therefore 2029 to 2037. Minnova confirmed that this correction does not affect the PEA's production figures, capital costs, or economic outcomes, which remain as originally reported, including total recovered gold of 621,500 ounces over a 10-year mine life.
Resource Expansion Drilling and Lower-Grade In-Pit Mineralization at PL Gold Mine
Minnova identified several resource expansion opportunities, noting the PL deposit remains open down-dip and along strike. Six drill holes completed during the 132-hole program were excluded from the current Mineral Resource Estimate database and will be incorporated into the planned Pre-Feasibility Study. Recent infill drilling also revealed wider zones of lower-grade disseminated mineralization within the open pits, with highlight intercepts including 0.78 g/t over 12.7 metres in hole M-26-046 and 0.49 g/t over 12.5 metres in hole M-25-013. The company stated this material could be stockpiled for deferred processing or directed to ore sorting.
Proposed $225,000 Debt Settlement via Common Share Issuance
Minnova intends to settle $225,000 of indebtedness by issuing 1,500,000 common shares at $0.15 per share. Of those shares, 1,366,666 will be issued to certain insiders, constituting a related-party transaction under Multilateral Instrument 61-101. The company expects to rely on exemptions from formal valuation and minority shareholder approval requirements. Issued shares will be subject to a four-month hold period, and closing remains conditional on receipt of regulatory approvals, including TSX Venture Exchange approval.