Highlights

  • Commissioning of 30-column DLE System and purification units now underway in Alberta.
  • Brine introduction into DLE system completed; full commissioning expected within one week.
  • Phase 1 results to support production of battery-grade lithium carbonate later this year.

E3 LITHIUM LTD. (TSXV: ETL) (FSE: OW3) (OTCQX: EEMMF) has announced that commissioning of Phase 1 of its Demonstration Facility is underway and proceeding as scheduled. The Phase 1 program is centered on operating the 30-column Direct Lithium Extraction (DLE) System and the polishing and purification equipment (Purification Units). These systems aim to produce a high-quality lithium chloride solution, a critical precursor for battery-grade lithium carbonate.

The company confirmed that final testing and operational reviews were completed last week, leading to the introduction of brine into the DLE System over the weekend. This step marks the first stage of commissioning and is expected to take roughly one week to reach full operational status. Once the DLE System is fully commissioned, the Purification Units will be brought online, allowing lithium chloride produced in the first stage to pass through purification and complete Phase 1 commissioning.

According to the company, the objectives of Phase 1 include verifying the assembly and performance of the equipment, confirming system functionality under real-time operating conditions, and producing lithium chloride at the required quality for downstream processing. Upon completion, the Demonstration Facility will transition to full operations and provide valuable process data.

E3 Lithium indicated that it has sufficient brine supply to support operations into early Q4 2025. The company plans to provide further updates as results from the Phase 1 campaign become available.

“The commissioning of Phase 1 of our Demonstration Facility highlights the equipment is in full working order and is an exciting next step for the advancement of this facility,” said Chris Doornbos, President and CEO. “The results from Phase 1 will ensure that our process is fully optimized and ready for Phase 2 of the Demonstration Facility that is set to begin later this fall.”

Phase 2 is expected to further refine the process, moving closer to commercial-scale production of battery-grade lithium carbonate. The results from Phase 1 are anticipated to play a key role in optimizing the technology and informing project economics.