Key Highlights

  • Eldorado fed first ore through the Skouries crushing circuit on July 20, 2026, starting staged commissioning of the northern Greece copper-gold mine
  • The project was about 94% complete at the end of Q1 2026, with first concentrate targeted for Q3 2026 and commercial production for Q4 2026
  • Steady-state Skouries output by 2028 is projected at 170,000-200,000 ounces of gold and 50-80 million pounds of copper annually
  • Q1 2026 gold output reached 100,358 ounces at an AISC of US$1,942 per ounce, with the average realized gold price at US$4,891 per ounce
  • Total Skouries capital estimate rose to about US$1.315 billion, up roughly US$155 million on labour, contractor and foreign-exchange pressures

A Milestone Decade in the Making

Eldorado Gold Corporation (TSX: ELD; NYSE: EGO) has moved a step closer to becoming a copper-gold producer. On July 20, 2026, the Vancouver-based miner announced that first ore had been fed through the crushing circuit at its Skouries project in northern Greece, marking the start of staged commissioning at a mine that has been under development for more than a decade. This milestone matters because Skouries anchors a growth plan that management says could lift gold production by roughly 40% between 2025 and 2027 while adding meaningful copper exposure. The transition from construction to production is now the central question facing the stock.

Eldorado's Three-Country Footprint

Eldorado is a mid-tier gold producer with operations across three countries. In Turkey it runs the Kisladag heap-leach mine and the higher-grade Efemcukuru underground mine. In Canada it owns the Lamaque complex in Quebec, its lowest-cost operation. In Greece it operates the Olympias polymetallic mine and the Stratoni holdings, alongside the Skouries development. The company reports in US dollars. For 2026, it has guided to total gold production of 490,000 to 590,000 ounces, with Lamaque expected to contribute 185,000 to 200,000 ounces, Kisladag 105,000 to 130,000, and Efemcukuru and Olympias 70,000 to 80,000 ounces each. Skouries is budgeted to add its first 60,000 to 100,000 ounces of gold this year.

The Milestone Itself: First Ore Crushed

The Skouries commissioning update is the most significant recent development. As of March 31, 2026, the project was about 94% complete, with more than 3,200 personnel on site. The company has stockpiled roughly 3.9 million tonnes of ore, including about 3.4 million tonnes of run-of-mine material, to support a steady ramp-up through the year. CEO George Burns called the crushing of first ore "an important milestone" that reflects "steady, safe progress" as the project moves through final construction and staged commissioning. Eldorado is targeting first copper-gold concentrate in the third quarter of 2026 and commercial production in the fourth, subject to final site energization, integrated commissioning and ramp-up. Circuits for grinding, flotation, concentrate handling and tailings are being progressively handed to operations.

Q1 2026: Strong Prices, Heavy Investment

First-quarter 2026 results underline both the strength of the gold price and the cost of building Skouries. Eldorado produced 100,358 ounces of gold and reported revenue of US$532.4 million. Net earnings were US$136.4 million, or US$0.69 per share, with adjusted net earnings of US$188.2 million. The average realized gold price was US$4,891 per ounce. All-in sustaining costs were US$1,942 per ounce sold, with total cash costs of US$1,470. Operating cash flow reached US$141.4 million, but free cash flow was negative US$129.1 million, reflecting US$135.6 million of Skouries investment in the quarter. The company ended March with US$629.7 million in cash. Lamaque was again the standout, producing 42,306 ounces at an AISC of US$1,370, while Efemcukuru carried the highest unit costs.

Why Skouries Changes the Whole Cost Profile

Skouries reshapes Eldorado's cost and commodity profile in a meaningful way. Management projects the mine will reach steady-state output of roughly 170,000 to 200,000 ounces of gold and 50 to 80 million pounds of copper a year by 2028. Because copper by-product credits offset gold costs, Eldorado has guided Skouries to an all-in sustaining cost of negative US$100 to positive US$200 per ounce once fully ramped up. That would make it among the company's cheapest sources of production and add copper exposure at a time when the metal is central to electrification demand.

Riding a Favourable Gold Price Cycle

Eldorado is advancing Skouries into an unusually favourable price environment, with gold trading near record levels through the first half of 2026. That backdrop has lifted mid-tier producers broadly, but it has also inflated construction and labour costs across the sector. The company has separately expanded its copper ambitions: in April 2026 it completed the acquisition of Foran Mining, adding the McIlvenna Bay copper-zinc-gold-silver project in Saskatchewan. Together with Skouries, the deal signals a deliberate tilt toward copper diversification, distinguishing Eldorado from pure-play gold peers while exposing it to a second, more cyclical metal market.

The Path to Free Cash Flow

The near-term opportunity is straightforward: converting a long-delayed construction project into cash flow. Eldorado has said Skouries is projected to deliver positive cash flow from the second half of 2026 onward, and its three-year outlook targets 2028 production of 640,000 to 740,000 ounces of gold plus 50 to 80 million pounds of copper. A successful ramp-up would move the company from a period of heavy capital outflow toward genuine free cash flow generation, potentially strengthening the balance sheet and supporting further growth or shareholder returns.

Where Execution Risk Remains

The risks are equally concrete. Skouries capital costs have already risen: the company revised its total project estimate to about US$1.315 billion, an increase of roughly US$155 million driven by labour, contractor and foreign-exchange pressures. Cumulative Phase 2 spending had reached US$1.116 billion by the end of the first quarter. Commissioning and ramp-up of a complex flotation operation can slip, and the concentrate and commercial-production targets remain conditional. Eldorado also carries country risk across Greece and Turkey, elevated unit costs at some mines, and exposure to swings in both gold and copper prices.

What to Watch in the Coming Months

Several markers will test the plan over the coming months. First is the timing of first concentrate, expected in the third quarter, and the pace of the ramp toward commercial production in the fourth. Second is whether Skouries capital costs hold at the revised estimate. Third is the leadership transition: Mr. Burns is due to retire in the third quarter of 2026, with President Christian Milau set to become chief executive. Fourth is copper price direction as the McIlvenna Bay project advances.

Conclusion

Eldorado Gold enters the second half of 2026 at a genuine inflection point. First ore through the Skouries crusher confirms the project has reached commissioning, and record gold prices have bolstered earnings and cash reserves. Yet the value case still hinges on execution: delivering concentrate on schedule, containing costs and ramping a new copper-gold mine safely. As of July 29, 2026, the shares traded in the low-C$40s on the TSX, for a market capitalization of roughly C$11 billion. The next two quarters will show whether the growth thesis translates into production.